00:00:00.320 --> 00:00:02.200
council is now 2pm and the ordinary

00:00:02.279 --> 00:00:05.280
meeting of Wednesday the 8th of May 2024

00:00:05.360 --> 00:00:07.559
will commence  I'll just make the

00:00:07.639 --> 00:00:08.960
announcement all Council meetings are

00:00:09.039 --> 00:00:11.119
live streamed to the internet and are

00:00:11.199 --> 00:00:13.240
recorded and then available for public

00:00:13.320 --> 00:00:14.759
viewing and archived on council's

00:00:14.839 --> 00:00:16.079
website

00:00:16.160 --> 00:00:20.199
www.begavalley.nsw.gov.au

00:00:23.559 --> 00:00:25.120
I'll also start by acknowledging Bega Valley Shire

00:00:25.199 --> 00:00:27.079
the traditional waterways and the airspace in which we

00:00:27.160 --> 00:00:28.640
are gathering

00:00:28.719 --> 00:00:30.800
today and under the Local Government Act

00:00:30.879 --> 00:00:32.240
and required to read the statement of

00:00:32.320 --> 00:00:33.840
ethical obligations the Mayor and

00:00:33.920 --> 00:00:35.320
councils reminded that they remain

00:00:35.399 --> 00:00:37.920
banned by the affirmation of offers made

00:00:38.000 --> 00:00:39.880
at the start of their Council term to

00:00:39.960 --> 00:00:41.520
undertake their civic duties in the best

00:00:41.600 --> 00:00:42.759
interest of the people of the Bega

00:00:42.840 --> 00:00:44.759
Valley Shire and to faithfully and

00:00:44.840 --> 00:00:46.439
impartially carry out the functions

00:00:46.520 --> 00:00:48.640
powers authorities and discretions

00:00:48.719 --> 00:00:49.840
vested in them under the Local

00:00:49.920 --> 00:00:51.200
Government Act or any other act to the

00:00:51.280 --> 00:00:53.439
best of their skill in their judgement

00:00:53.520 --> 00:00:54.799
the Mayor and counselors are also

00:00:54.880 --> 00:00:56.320
reminded of the requirement for

00:00:56.399 --> 00:00:57.960
disclosure of conflicts of interest in

00:00:58.039 --> 00:00:59.920
relation to items listed for

00:01:00.000 --> 00:01:02.759
consideration on the agenda or which are

00:01:02.840 --> 00:01:04.280
considered at this meeting in accordance

00:01:04.359 --> 00:01:05.840
with the code of conduct and code of

00:01:05.920 --> 00:01:07.319
meeting practice

00:01:07.400 --> 00:01:09.480
apologies we have apologies

00:01:09.560 --> 00:01:12.200
from councelor Griff and councelor Robin

00:01:12.280 --> 00:01:14.319
anyone like to move they be accepted

00:01:14.400 --> 00:01:17.159
councelor O'Neill councelor Seckold all in favor

00:01:17.239 --> 00:01:19.359
carried unanimously confirmation of the

00:01:19.439 --> 00:01:22.519
minutes held on the 17th of April 2024

00:01:22.599 --> 00:01:24.000
as circulated be taken as read and

00:01:24.079 --> 00:01:25.519
confirmed

00:01:25.599 --> 00:01:29.120
mover  Councilor Wright Councilor Porter

00:01:29.200 --> 00:01:30.480
all those in favour

00:01:30.560 --> 00:01:33.040
carried unanimously declarations any

00:01:33.120 --> 00:01:36.400
declarations Mr CEO no Mr Mayor public for

00:01:36.480 --> 00:01:38.439
today there's no petitions no Mayoral

00:01:38.519 --> 00:01:41.239
minute no urgent business staff reports

00:01:41.319 --> 00:01:42.719
community environment there are none

00:01:42.799 --> 00:01:44.799
staff reports assets and operations none

00:01:44.879 --> 00:01:46.640
staff reports business and governance

00:01:46.719 --> 00:01:50.079
10.1 quarterly budget review statement

00:01:50.159 --> 00:01:53.239
council's any questions for the staff

00:01:53.319 --> 00:01:56.719
have a couple but someone else councelor

00:01:56.799 --> 00:02:00.120
Allen thank you Mr Mayor just briefly 

00:02:00.200 --> 00:02:01.439
to the

00:02:01.519 --> 00:02:04.359
 the head of the finance department

00:02:04.439 --> 00:02:07.079
under cash and investments we indicate

00:02:07.159 --> 00:02:10.000
that  our present investments are  

00:02:10.080 --> 00:02:15.240
26.7 million but they're

00:02:15.319 --> 00:02:18.120
invisaging that they fall

00:02:18.199 --> 00:02:21.280
significantly by June approximately 50

00:02:21.360 --> 00:02:23.479
million  just for

00:02:23.560 --> 00:02:25.680
the people observing the meeting and

00:02:25.759 --> 00:02:27.280
reading these documents that's a massive

00:02:27.360 --> 00:02:29.439
amount of money to spending what's it

00:02:29.520 --> 00:02:30.280
now 

00:02:30.360 --> 00:02:31.879
May purely 7 weeks between now and the

00:02:31.960 --> 00:02:34.039
end of June so could we just have an

00:02:34.120 --> 00:02:36.560
explanation number one and number two if

00:02:36.639 --> 00:02:39.319
if the figure that's been semi for as

00:02:39.400 --> 00:02:42.360
being the figure that will be available

00:02:42.439 --> 00:02:44.840
in June do we adjust our

00:02:44.919 --> 00:02:46.960
interest budgeting according to that

00:02:47.039 --> 00:02:49.919
semiford or do we just  not budget 

00:02:50.000 --> 00:02:51.159
we budget on the figure that we've got

00:02:51.240 --> 00:02:54.879
presently invested

00:03:07.080 --> 00:03:09.240
 through you Mr Mayor the amount that

00:03:09.319 --> 00:03:13.960
we have  included in the investment

00:03:14.039 --> 00:03:16.719
report is at 8 point in time so it's at

00:03:16.800 --> 00:03:18.639
the end of April the

00:03:18.719 --> 00:03:21.439
73.6 estimated result for 30 June

00:03:21.520 --> 00:03:23.719
? all Grant all income and

00:03:23.800 --> 00:03:27.080
expenses will be as budgeted  so

00:03:27.159 --> 00:03:29.280
changes or delays in capital operational

00:03:29.360 --> 00:03:31.639
projects and timing of grant payments

00:03:31.719 --> 00:03:34.400
will have an impact on this result 

00:03:34.479 --> 00:03:35.879
budget managers reviewed all their

00:03:35.960 --> 00:03:37.840
expenses and income budgets to minimize

00:03:37.919 --> 00:03:39.159
a potential

00:03:39.240 --> 00:03:42.800
impact but we can't completely re remove

00:03:42.879 --> 00:03:45.120
that  potential change

00:03:45.199 --> 00:03:48.560
there in regard to the budgeting for

00:03:48.639 --> 00:03:51.319
interest  we budget on the income that

00:03:51.400 --> 00:03:54.080
is in our bank account that earns

00:03:54.159 --> 00:03:57.439
interest so each quarter we're looking

00:03:57.520 --> 00:04:00.680
at their investment budget to ensure

00:04:00.759 --> 00:04:02.479
that it's keeping track of where it is

00:04:02.560 --> 00:04:05.039
we're being conservative each quarter 

00:04:05.120 --> 00:04:07.560
but each quarter we increase it 

00:04:07.639 --> 00:04:09.319
because we don't have an understanding

00:04:09.400 --> 00:04:11.039
when we set that budget of the timing of

00:04:11.120 --> 00:04:14.280
the capital projects  and the expenses

00:04:14.360 --> 00:04:16.319
in those spaces and they're quite large

00:04:16.399 --> 00:04:20.360
expenses that could happen quite

00:04:24.560 --> 00:04:26.920
quickly 

00:04:27.000 --> 00:04:29.920
questions I have a couple just coup

00:04:30.000 --> 00:04:31.439
around the same I just like to confirm

00:04:31.519 --> 00:04:33.399
the projected year end results before

00:04:33.480 --> 00:04:38.079
grants and and  of 11.6 million in the

00:04:38.160 --> 00:04:41.279
present time  that is without the

00:04:41.360 --> 00:04:44.000
financial assistance grants payment and

00:04:44.079 --> 00:04:45.279
we haven't had any indication whether

00:04:45.360 --> 00:04:47.759
that's going to be paid in advance

00:04:47.839 --> 00:04:51.160
again through you Mr Mayor we don't have

00:04:51.240 --> 00:04:52.639
an indication last year it happened

00:04:52.720 --> 00:04:54.600
quite late in June  so it's not

00:04:54.680 --> 00:04:56.160
included in these

00:04:56.240 --> 00:04:58.480
figures what  is included in these

00:04:58.560 --> 00:05:00.680
figures  are some grants that will

00:05:00.759 --> 00:05:04.000
carry over multiple years that 

00:05:04.079 --> 00:05:07.240
income's been received

00:05:07.519 --> 00:05:11.279
for Mr Mayor can just add to that looking and

00:05:11.360 --> 00:05:12.600
this is an issue we always face looking

00:05:12.680 --> 00:05:15.000
at the income statement result in

00:05:15.079 --> 00:05:16.800
isolation can sometimes be a little bit

00:05:16.879 --> 00:05:19.319
problematic and one example in the

00:05:19.399 --> 00:05:22.199
variations that are included for

00:05:22.279 --> 00:05:27.480
recommendation here is an additional 

00:05:27.560 --> 00:05:30.480
significant grant coming in operating

00:05:30.560 --> 00:05:31.600
income

00:05:31.680 --> 00:05:34.160
for road expenditure but the actual

00:05:34.240 --> 00:05:36.519
expenditure is going to be utilized on

00:05:36.600 --> 00:05:38.879
capital works so you don't actually see

00:05:38.959 --> 00:05:41.319
that impact in the income statement and

00:05:41.399 --> 00:05:42.720
if you look at the recommended

00:05:42.800 --> 00:05:44.600
variations so end of

00:05:44.680 --> 00:05:47.319
year cash and investment positions it's

00:05:47.399 --> 00:05:49.680
actually only a roughly $2 million

00:05:49.759 --> 00:05:53.160
increase not  that significant a

00:05:53.240 --> 00:05:54.920
change so there's a number of factors

00:05:55.000 --> 00:05:56.199
that drive that and that's just one

00:05:56.279 --> 00:05:58.360
example I provided the ? material yeah

00:05:58.439 --> 00:06:00.959
and a question was going to ask

00:06:01.040 --> 00:06:03.319
about .4 and the grant contribution we had

00:06:03.399 --> 00:06:06.360
the 4.5 million of the road so local

00:06:06.439 --> 00:06:08.839
pothole money and I was wondering where

00:06:08.920 --> 00:06:11.360
that comes into the budget so that basically

00:06:11.439 --> 00:06:12.800
explains that yeah that's that's the

00:06:12.879 --> 00:06:14.439
explanation for that that's actually the

00:06:14.519 --> 00:06:16.160
item that comes in as operating income

00:06:16.240 --> 00:06:18.360
but then predominantly getting spent on

00:06:18.439 --> 00:06:20.240
capital expenditure we are allowed to

00:06:20.319 --> 00:06:22.360
account for it that way which is similar

00:06:22.439 --> 00:06:24.120
to how we account for federal roads to

00:06:24.199 --> 00:06:25.600
recovery grants when they come in as

00:06:25.680 --> 00:06:27.319
well often get spent on capital works

00:06:27.399 --> 00:06:30.000
but the income is operating

00:06:30.079 --> 00:06:32.920
so on the capital grants while we're on

00:06:33.000 --> 00:06:35.160
that the 16 million being deferred off

00:06:35.240 --> 00:06:37.160
there's quite a list there at Note 5

00:06:37.240 --> 00:06:38.759
could you give us some explanations of

00:06:38.839 --> 00:06:39.920
some of those of why they've been

00:06:40.000 --> 00:06:42.439
deferred or delayed specifically in

00:06:42.519 --> 00:06:44.680
regard to the bridge ones  I think you

00:06:44.759 --> 00:06:45.959
probably can elaborate for the community

00:06:46.040 --> 00:06:47.319
on the sports   1   the 8 million for the

00:06:47.399 --> 00:06:49.199
Bega sports ground as well what was the

00:06:49.279 --> 00:06:51.480
hold up

00:06:51.560 --> 00:06:53.839
there yeah through to me I'm happy to take

00:06:53.920 --> 00:06:56.639
a couple of the  respond to a couple

00:06:56.720 --> 00:06:58.319
of those the more significant ones there

00:06:58.399 --> 00:07:01.160
is a couple of bridge related projects in 

00:07:01.240 --> 00:07:05.040
particular  Richies lagoons an example

00:07:05.120 --> 00:07:06.759
Dignam's Creeks another example which

00:07:06.839 --> 00:07:08.879
are relatively large projects delayed

00:07:08.959 --> 00:07:12.079
mainly due to internal

00:07:12.160 --> 00:07:14.199
resourcing with people being available

00:07:14.279 --> 00:07:15.639
to deliver those projects and the

00:07:15.720 --> 00:07:17.959
management of those and we're addressing

00:07:18.040 --> 00:07:19.519
those at the moment those particular

00:07:19.600 --> 00:07:22.720
couple and then another one that you

00:07:22.800 --> 00:07:25.040
alluded to was a bigger sporting complex

00:07:25.120 --> 00:07:27.480
it's a significant impact on that  or

00:07:27.560 --> 00:07:28.839
component of that figure you just

00:07:28.920 --> 00:07:30.759
referred to

00:07:30.839 --> 00:07:33.240
it has mainly been delayed in the

00:07:33.319 --> 00:07:37.000
current financial year  due to the

00:07:37.079 --> 00:07:39.480
need to go through a tender negotiation

00:07:39.560 --> 00:07:42.879
process partially where as councilor is

00:07:42.959 --> 00:07:44.839
aware the tenders came in outside of

00:07:44.920 --> 00:07:46.399
what was available within the budget so

00:07:46.480 --> 00:07:48.279
we had an extended negotiation process

00:07:48.360 --> 00:07:51.759
to reduce the cost which in some savings

00:07:51.839 --> 00:07:53.560
then at the same time we needed to wait

00:07:53.639 --> 00:07:55.399
for state government confirmation of

00:07:55.480 --> 00:07:56.879
availability of funding for that to

00:07:56.959 --> 00:07:58.800
continue so a couple of factors delayed

00:07:58.879 --> 00:07:59.920
that one

00:08:00.000 --> 00:08:01.519
which is why the recommendations here on

00:08:01.600 --> 00:08:04.439
those of the other large material one is

00:08:04.519 --> 00:08:06.480
the Bega water treatment plant which is

00:08:06.560 --> 00:08:09.319
several million dollars as well the 

00:08:09.399 --> 00:08:12.040
main cause of delay for that one is

00:08:12.120 --> 00:08:14.839
actually around a what I'll describe as

00:08:14.920 --> 00:08:16.800
a change of scope required from the New

00:08:16.879 --> 00:08:18.639
South Wales government specifically New

00:08:18.720 --> 00:08:20.480
South Wales Health on what the solution

00:08:20.560 --> 00:08:23.560
we actually constructed that site is and

00:08:23.639 --> 00:08:26.360
then waiting for the New South Wales

00:08:26.439 --> 00:08:28.360
government to agree to fund the

00:08:28.439 --> 00:08:30.959
additional funds that are for the 

00:08:31.040 --> 00:08:32.559
higher scope of what they want us to

00:08:32.639 --> 00:08:35.240
build which did eventually come

00:08:35.320 --> 00:08:37.519
600,000  additional we received for

00:08:37.600 --> 00:08:39.480
that but that caused the delay to that

00:08:39.559 --> 00:08:40.960
one and pushed it in the next financial

00:08:41.039 --> 00:08:42.039
year so they're probably the most

00:08:42.120 --> 00:08:43.840
material ones in that

00:08:43.919 --> 00:08:46.240
list else there's any further questions

00:08:46.320 --> 00:08:48.759
other councilors Councilor Porter yes just

00:08:48.840 --> 00:08:50.440
one good question could you please

00:08:50.519 --> 00:08:53.159
indicate  what savings were achieved

00:08:53.240 --> 00:08:55.440
as a result of the service review

00:08:55.519 --> 00:08:58.519
process

00:09:00.519 --> 00:09:05.840
Mr Mayor I am not quite sure what is

00:09:05.919 --> 00:09:07.639
being asked because the service review

00:09:07.720 --> 00:09:11.879
process that has  been getting

00:09:11.960 --> 00:09:14.039
undertaken was only recently worked

00:09:14.120 --> 00:09:16.320
through with counselors and from a staff

00:09:16.399 --> 00:09:18.559
perspective there isn't any additional

00:09:18.639 --> 00:09:21.559
recommended changes in this budget 

00:09:21.639 --> 00:09:24.480
budget review resulting out of that 

00:09:24.559 --> 00:09:26.840
there has been what I call some

00:09:26.919 --> 00:09:30.080
relatively minor scale financial impact

00:09:30.159 --> 00:09:31.559
changes that have occur but they're

00:09:31.639 --> 00:09:33.080
certainly not material in the context of

00:09:33.159 --> 00:09:34.919
the overall

00:09:35.000 --> 00:09:37.759
budget councelors any further questions have

00:09:37.840 --> 00:09:39.799
the recommendation councilors councelor

00:09:39.879 --> 00:09:41.799
Allen councelor Nadin

00:09:41.879 --> 00:09:45.240
wish to speak to councelor

00:09:45.320 --> 00:09:47.720
Allen the recommendation all those in

00:09:47.799 --> 00:09:50.039
favor carried unanimously thanks

00:09:50.120 --> 00:09:53.120
councilors item 10.2 exhibition of

00:09:53.200 --> 00:09:55.559
internal planning reporting documents

00:09:55.639 --> 00:09:58.279
quite a number of documents counselors

00:09:58.360 --> 00:10:00.000
 sometimes in the past we've had

00:10:00.080 --> 00:10:04.159
counselors submit  instead of on the

00:10:04.240 --> 00:10:06.159
floor counselors submit any changes

00:10:06.240 --> 00:10:07.799
they'd like so that staff can deal with

00:10:07.879 --> 00:10:09.120
those instead of us dealing with them on

00:10:09.200 --> 00:10:10.679
the floor between now and through the

00:10:10.759 --> 00:10:12.799
exhibition period be good for the staff

00:10:12.879 --> 00:10:14.240
if we could follow that process would be

00:10:14.320 --> 00:10:16.279
great but understand that there'll be

00:10:16.360 --> 00:10:17.759
some negotiations on the floor when it

00:10:17.840 --> 00:10:20.759
comes back to us to be

00:10:20.840 --> 00:10:23.080
adopted I just clarify something this

00:10:23.159 --> 00:10:24.639
has being very semantic when you

00:10:24.720 --> 00:10:26.080
introduce this item it's actually

00:10:26.159 --> 00:10:27.720
exhibition of the integrated planning

00:10:27.799 --> 00:10:29.679
and Reporting documents you you use the

00:10:29.759 --> 00:10:32.840
term internal so this is actually sorry

00:10:32.919 --> 00:10:36.000
public integrated plan sorry about that

00:10:36.080 --> 00:10:38.440
my poor language counc you've got a

00:10:38.519 --> 00:10:41.399
point three you'd like to add to one and

00:10:41.480 --> 00:10:44.960
two yeah questions  thank you Mr Mayor

00:10:45.039 --> 00:10:46.720
so just with a budget cash flow

00:10:46.799 --> 00:10:50.799
statement  for option b which is the

00:10:50.879 --> 00:10:53.200
current trajectory of council with the

00:10:53.279 --> 00:10:56.200
assets and services SRV just had two

00:10:56.279 --> 00:10:59.879
questions regarding this so we've got a

00:10:59.960 --> 00:11:02.279
a cash so you're talking the long-term

00:11:02.360 --> 00:11:04.120
financial plan  the long-term

00:11:04.200 --> 00:11:05.519
financial plan sure but it's actually in

00:11:05.600 --> 00:11:08.039
the budget because it's 202

00:11:08.120 --> 00:11:12.159
2425  and that is the

00:11:12.240 --> 00:11:16.320
26306 million I'm just wondering whether

00:11:16.399 --> 00:11:22.919
that figure includes the recent  legal

00:11:23.000 --> 00:11:26.440
  fees and claim that was made

00:11:26.519 --> 00:11:29.840
against Council

00:11:30.159 --> 00:11:33.639
or not in the expenses you say  no

00:11:33.720 --> 00:11:36.039
just in cash in cash flow because it'll

00:11:36.120 --> 00:11:38.840
have to be I asse that it's going to

00:11:38.919 --> 00:11:40.360
change that figure unless it's already

00:11:40.440 --> 00:11:44.200
changed which is the question I'm

00:11:46.759 --> 00:11:49.840
asking

00:11:49.919 --> 00:11:54.080
oh three Mr Mayor at the time of the QB

00:11:54.159 --> 00:11:57.000
the the budget includes the results of

00:11:57.080 --> 00:11:57.639
the

00:11:57.720 --> 00:12:00.480
qbrs which is to the 31st of March any

00:12:00.559 --> 00:12:03.240
changes post 31st of March have not been

00:12:03.320 --> 00:12:06.039
incorporated or included in any of the

00:12:06.120 --> 00:12:09.919
financial statements that's no that's a

00:12:10.000 --> 00:12:12.919
no how much was it just one point

00:12:13.000 --> 00:12:15.279
because it might not

00:12:15.360 --> 00:12:18.000
actually anything it might actually not

00:12:18.080 --> 00:12:21.519
impact cash flow if we decide to make

00:12:21.600 --> 00:12:25.120
service reductions or change the budget

00:12:25.200 --> 00:12:27.039
so I guess what I'm trying to say is

00:12:27.120 --> 00:12:28.679
between now and when we actually adopt

00:12:28.759 --> 00:12:31.279
this budget

00:12:31.360 --> 00:12:33.039
ific

00:12:33.120 --> 00:12:35.799
change through Mr Mayor there is still

00:12:35.879 --> 00:12:37.679
potential of some changes and one of the

00:12:37.759 --> 00:12:39.519
issues in forming budgets is always the

00:12:39.600 --> 00:12:41.279
point in time that you draw a line in

00:12:41.360 --> 00:12:43.960
the sand use information and then make

00:12:44.039 --> 00:12:45.639
adjustments down the track so there is a

00:12:45.720 --> 00:12:48.440
chance that  we Mayor need to make an

00:12:48.519 --> 00:12:49.639
adjustment

00:12:49.720 --> 00:12:54.039
for additional unbudgeted expenditure

00:12:54.120 --> 00:12:56.480
there's also a chance that we Mayor not

00:12:56.559 --> 00:12:58.000
and we just don't completely know that

00:12:58.080 --> 00:13:00.440
answer yet and we also don't know the

00:13:00.519 --> 00:13:02.039
answer necessarily on what the quant

00:13:02.120 --> 00:13:03.840
will be

00:13:03.919 --> 00:13:07.320
yet the quant was finished I mean

00:13:07.399 --> 00:13:09.360
because I'm not talking about the latest

00:13:09.440 --> 00:13:10.759
one I'm only talking about the original

00:13:10.840 --> 00:13:12.879
for $900,000 so we know what the quant

00:13:12.960 --> 00:13:16.200
is there that was the claim Am I Wrong

00:13:16.279 --> 00:13:18.639
why you looking at me

00:13:18.720 --> 00:13:22.080
funny Mr Mayor I'm not going to publicly

00:13:22.159 --> 00:13:24.679
diab we don't know completely whether

00:13:24.759 --> 00:13:26.759
that's the end figure or not but it Mayor

00:13:26.840 --> 00:13:30.159
not be that it's the end of the matter

00:13:30.240 --> 00:13:33.200
a long way to go sure but it's the money

00:13:33.279 --> 00:13:35.840
has left our account so therefore it has

00:13:35.919 --> 00:13:38.559
to be budgetable regardless of if

00:13:38.639 --> 00:13:41.480
we decide to I don't know how much of

00:13:41.559 --> 00:13:44.879
this is is any of this confidential so

00:13:44.960 --> 00:13:46.639
three Mr Mayor again the point I was

00:13:46.720 --> 00:13:49.480
making was that this

00:13:49.559 --> 00:13:52.159
isn't let's let's take a a broader view

00:13:52.240 --> 00:13:53.960
of this there are certain times where at

00:13:54.039 --> 00:13:56.399
a point in time we asse we don't need

00:13:56.480 --> 00:13:58.279
to do something then at another point in

00:13:58.360 --> 00:13:59.960
time we do need to do something and then

00:14:00.039 --> 00:14:01.600
we change our budget to reflect that and

00:14:01.679 --> 00:14:03.279
then down the track again we realized

00:14:03.360 --> 00:14:04.639
that what we thought we had to do at

00:14:04.720 --> 00:14:06.679
another point in time wasn't right and

00:14:06.759 --> 00:14:09.399
we adjust again so at the point in time

00:14:09.480 --> 00:14:11.840
that we  do provide a final

00:14:11.919 --> 00:14:15.360
recommended budget to council will be

00:14:15.440 --> 00:14:17.399
potentially have some changes based on

00:14:17.480 --> 00:14:19.679
known factors at that point in time or

00:14:19.759 --> 00:14:21.279
it Mayor be that it happens at the next

00:14:21.360 --> 00:14:23.120
quarterly budget

00:14:23.200 --> 00:14:27.879
review okay well I will jot that down as

00:14:27.960 --> 00:14:29.600
we will have something by the time it

00:14:29.679 --> 00:14:31.679
comes back to council because this is

00:14:31.759 --> 00:14:34.639
the point in time I mean like I don't

00:14:34.720 --> 00:14:35.720
know what you're forecasting whe they're

00:14:35.799 --> 00:14:36.559
going to have a winning court or

00:14:36.639 --> 00:14:38.919
something like that at the moment

00:14:39.000 --> 00:14:40.399
there's an amount of money that has been

00:14:40.480 --> 00:14:42.279
expended and I'm trying to work out

00:14:42.360 --> 00:14:44.120
whether it's been it's going to be

00:14:44.200 --> 00:14:46.440
reflected in this docent and you're

00:14:46.519 --> 00:14:48.879
saying it is because that's the point in

00:14:48.960 --> 00:14:53.000
time and that's the of this three Mr

00:14:53.080 --> 00:14:55.039
Mayor what I said before was and this is

00:14:55.120 --> 00:14:57.240
what the manager said was when this

00:14:57.320 --> 00:14:59.879
information was prepared prior to today

00:14:59.960 --> 00:15:03.320
that wasn't known it is now known and

00:15:03.399 --> 00:15:06.080
yeah and by the time we bring a final

00:15:06.159 --> 00:15:09.879
budget back to Council in that will be

00:15:09.960 --> 00:15:11.600
considered that's fine thank you  so

00:15:11.679 --> 00:15:13.399
that's fine  in these special

00:15:13.480 --> 00:15:16.720
variations so you've got U sorry I

00:15:16.799 --> 00:15:19.279
should just clarify for everyone in our

00:15:19.360 --> 00:15:21.320
re Revenue policy we obviously label all

00:15:21.399 --> 00:15:22.519
of our special

00:15:22.600 --> 00:15:24.879
variations and we've got our most recent

00:15:24.960 --> 00:15:26.679
one which is the

00:15:26.759 --> 00:15:29.679
19.6% and that comes in it

00:15:29.759 --> 00:15:31.559
65

00:15:31.639 --> 00:15:34.480
million 

00:15:34.559 --> 00:15:39.679
yeah oh yes 140 of the  of plan and

00:15:39.759 --> 00:15:45.639
budget so that's  in the revenue

00:15:45.720 --> 00:15:49.720
policy so yeah so it's I'm just trying

00:15:49.799 --> 00:15:53.000
to work out here so the application

00:15:53.080 --> 00:15:54.360
requested a permanent increase to

00:15:54.440 --> 00:15:57.919
General rates of 24% last in the no this

00:15:58.000 --> 00:16:00.279
financial year that we're in now 

00:16:00.360 --> 00:16:04.000
inclusive of the rate Peg and then 19.6

00:16:04.080 --> 00:16:05.759
so and then it says later on the SB will

00:16:05.840 --> 00:16:08.480
provide additional rates income of 6.5

00:16:08.559 --> 00:16:11.600
in 20242 should that be should that

00:16:11.679 --> 00:16:14.120
figure

00:16:14.399 --> 00:16:17.759
there include the 19.6 because that's

00:16:17.840 --> 00:16:22.039
ongoing now so that'll be a figure every

00:16:22.120 --> 00:16:23.320
year with

00:16:23.399 --> 00:16:27.480
CP shouldn't it with right P yeah with

00:16:27.559 --> 00:16:30.559
right

00:16:31.320 --> 00:16:33.879
I'm just trying to say this is only the

00:16:33.960 --> 00:16:36.799
2425 like the revenue out of this should

00:16:36.879 --> 00:16:40.559
be 11 million if I'm not

00:16:42.440 --> 00:16:45.039
mistaken

00:16:45.120 --> 00:16:48.600
oh this table represents the revenue in

00:16:48.679 --> 00:16:52.159
2425 so in 2425 the revenue from that

00:16:52.240 --> 00:16:55.440
special variation is 6.5 million on top

00:16:55.519 --> 00:16:59.320
of our previous year's  figure

00:16:59.399 --> 00:17:01.399
so it's not an acculated figure this

00:17:01.480 --> 00:17:04.079
is the revenue from the SRV there is a

00:17:04.160 --> 00:17:06.200
table within the docent and I will try

00:17:06.279 --> 00:17:09.880
and find the page number the rep sorry

00:17:09.960 --> 00:17:13.799
on page 133 you'll find we have provided

00:17:13.880 --> 00:17:16.279
a smary of Where the

00:17:16.359 --> 00:17:19.880
11 million do worth of SRV will be spent

00:17:19.960 --> 00:17:22.240
oh okay I'm it's actually a general

00:17:22.319 --> 00:17:23.839
question it's a general question

00:17:23.920 --> 00:17:25.519
regarding special variations because you

00:17:25.599 --> 00:17:27.319
know like libraries Gallery tourism we

00:17:27.400 --> 00:17:29.400
read 1.1

00:17:29.480 --> 00:17:31.519
that just and that changes every year it

00:17:31.599 --> 00:17:36.319
goes up so next year in know in the

00:17:36.400 --> 00:17:39.200
budget for 2526 will there be any

00:17:39.279 --> 00:17:40.880
mention of the asset renewal and

00:17:40.960 --> 00:17:42.519
services

00:17:42.599 --> 00:17:46.279
SRV the table that you're referring to T

00:17:46.359 --> 00:17:48.799
on page 140 includes all of the current

00:17:48.880 --> 00:17:51.400
SVS and the value of that SV in this

00:17:51.480 --> 00:17:53.359
current year so yes the asset and

00:17:53.440 --> 00:17:56.680
services  SRV will be included and it

00:17:56.759 --> 00:17:58.880
will be a increase on the rate Peg the

00:17:58.960 --> 00:18:00.759
rate Peg increase on top of that which

00:18:00.839 --> 00:18:02.279
we don't know at this

00:18:02.359 --> 00:18:04.839
point yeah so that's fine because this

00:18:04.920 --> 00:18:06.880
is the second year of the rate increase

00:18:06.960 --> 00:18:10.359
shouldn't that say $1

00:18:10.440 --> 00:18:12.880
million The Heading at the top of the T

00:18:12.960 --> 00:18:14.799
table that you're looking at is the

00:18:14.880 --> 00:18:16.400
revenue for

00:18:16.480 --> 00:18:19.960
2425  and like all of those SVS those

00:18:20.039 --> 00:18:23.000
SVS in the current year bring in this

00:18:23.079 --> 00:18:26.720
much money so the library SRV brings in

00:18:26.799 --> 00:18:29.440
last year's plus the rate Peg and so

00:18:29.519 --> 00:18:31.839
therefore we only bringing in what for

00:18:31.920 --> 00:18:34.319
The Current financial year the impact is

00:18:34.400 --> 00:18:37.799
on that the

00:18:37.880 --> 00:18:40.440
srvs I'll trying next

00:18:40.519 --> 00:18:42.839
year's that's not next year's numbers

00:18:42.920 --> 00:18:44.200
that's not next year's numbers yet

00:18:44.279 --> 00:18:46.799
without 19% hasn't come into play yet

00:18:46.880 --> 00:18:48.720
right the moment we're only dealing with

00:18:48.799 --> 00:18:49.400
the

00:18:49.480 --> 00:18:52.480
24% which is the 6.5 you're getting the

00:18:52.559 --> 00:18:54.359
11 milon you're taking the whole 43% in

00:18:54.440 --> 00:18:58.880
one hit in one hit okay that's fine so

00:18:58.960 --> 00:19:00.880
 sorry can I just go back to that that

00:19:00.960 --> 00:19:05.200
is the income we expect for 2425 so that

00:19:05.279 --> 00:19:06.119
is our

00:19:06.200 --> 00:19:09.319
19.6% yeah in a 2425 figure that's right

00:19:09.400 --> 00:19:13.400
yes in yeah in addition to the original

00:19:13.480 --> 00:19:16.799
24% corre and we have index SE as well

00:19:16.880 --> 00:19:20.799
we should have included that

00:19:22.000 --> 00:19:24.200
here sorry through you Mr Mayor when the

00:19:24.279 --> 00:19:25.920
documents are adopted that figure will

00:19:26.000 --> 00:19:27.279
be amended right now we're putting a

00:19:27.359 --> 00:19:29.519
budget on exhib

00:19:29.599 --> 00:19:31.720
that has the SV recommended once it's

00:19:31.799 --> 00:19:33.759
adopted the do the documents once they

00:19:33.839 --> 00:19:35.960
come back will indic in in that table

00:19:36.039 --> 00:19:37.480
indicate what the full amount of the

00:19:37.559 --> 00:19:40.759
2year SRV is so at the moment this is a

00:19:40.839 --> 00:19:42.480
draft docent we're putting forward for

00:19:42.559 --> 00:19:44.599
recommendation including the proposed

00:19:44.680 --> 00:19:47.000
19.6 because not so the two will come

00:19:47.079 --> 00:19:48.279
together when we're when we're putting

00:19:48.359 --> 00:19:49.759
the documents for

00:19:49.839 --> 00:19:56.960
recommendation aded half that's fine but

00:19:59.400 --> 00:20:02.240
oh sorry but that's fine anyway so for

00:20:02.319 --> 00:20:03.880
no that's okay but you understand what

00:20:03.960 --> 00:20:05.960
I'm saying then forever more after this

00:20:06.039 --> 00:20:07.599
it will be listed there and it will say

00:20:07.680 --> 00:20:09.839
11 and it will go up by whatever that's

00:20:09.920 --> 00:20:12.880
it okay cool glad we got that so sorry

00:20:12.960 --> 00:20:13.720
Mayorbe

00:20:13.799 --> 00:20:17.720
I'm  so  few more questions 

00:20:17.799 --> 00:20:20.880
through the  section just so you know

00:20:20.960 --> 00:20:25.880
Capital program so 124 councelor 

00:20:25.960 --> 00:20:29.079
O'Neal thank you so that's okay so got

00:20:29.160 --> 00:20:31.519
Grant income of a million dollar for and

00:20:31.599 --> 00:20:32.880
I've just got probably about six or

00:20:32.960 --> 00:20:34.319
seven of these Mr M so if you'll bear

00:20:34.400 --> 00:20:36.799
with me so a million dollar for the

00:20:36.880 --> 00:20:39.440
burmu indoor sports Stadi upgrade if

00:20:39.519 --> 00:20:41.799
you could just what what is that upgrade

00:20:41.880 --> 00:20:43.519
for is it a renewal or is it an

00:20:43.599 --> 00:20:45.640
extension an

00:20:45.720 --> 00:20:48.799
update three Mr Mayor it's for internal

00:20:48.880 --> 00:20:50.400
improvements and that was funded out of

00:20:50.480 --> 00:20:52.640
the  bushire Local Economic Recovery

00:20:52.720 --> 00:20:54.319
Fund

00:20:54.400 --> 00:20:56.839
yeah yeah so it just says he upgrade

00:20:56.920 --> 00:20:59.200
that's all so it's kind of a renewal is

00:20:59.279 --> 00:21:00.599
isn't it

00:21:00.680 --> 00:21:03.720
yeah that  the

00:21:03.799 --> 00:21:07.839
760 for biger lorial swimming pool

00:21:07.920 --> 00:21:10.519
that's still budgeted for isn't it the

00:21:10.599 --> 00:21:13.680
760 there which is for that's reserve

00:21:13.759 --> 00:21:16.599
for the design work isn't it so it's the

00:21:16.680 --> 00:21:18.799
long-term financial plan that those

00:21:18.880 --> 00:21:22.720
works are impacted isn't it yeah so

00:21:22.799 --> 00:21:25.279
three Mr Mayor as Council will recall

00:21:25.359 --> 00:21:27.000
we've always said that that project is

00:21:27.079 --> 00:21:28.880
going to need significant Grant funding

00:21:28.960 --> 00:21:31.799
to build it  but in order to get any

00:21:31.880 --> 00:21:33.279
grant funding we need to get to the

00:21:33.359 --> 00:21:34.880
point where as close to shovel ready as

00:21:34.960 --> 00:21:36.680
possible so those funds are to get it to

00:21:36.759 --> 00:21:38.119
the point where we can chase the money

00:21:38.200 --> 00:21:41.359
we need to build I guess that what I was

00:21:41.440 --> 00:21:43.240
referring to was I think there was Mayorbe

00:21:43.319 --> 00:21:45.599
$2 million in the long-term financial

00:21:45.680 --> 00:21:48.359
plan in the next three years I think it

00:21:48.440 --> 00:21:54.240
was for  just budgeted for internal 

00:21:54.319 --> 00:21:57.359
resource to match grant funding that

00:21:57.440 --> 00:21:58.920
money

00:21:59.000 --> 00:22:02.200
yeah so three Mr Mayor off the top of my

00:22:02.279 --> 00:22:03.880
head we originally had a long-term

00:22:03.960 --> 00:22:06.000
financial plan that

00:22:06.079 --> 00:22:11.759
assed  25%  grant funding and now

00:22:11.839 --> 00:22:15.799
that model is going to asse more

00:22:15.880 --> 00:22:17.400
Council

00:22:17.480 --> 00:22:20.880
contribution more grunding contri 

00:22:20.960 --> 00:22:22.160
sorry yeah more grant funding

00:22:22.240 --> 00:22:26.839
contribution less Council to account for

00:22:26.920 --> 00:22:30.000
Council contributing to

00:22:30.079 --> 00:22:32.319
projects  and just a few more here

00:22:32.400 --> 00:22:33.839
playground renewals what's the

00:22:33.920 --> 00:22:37.640
playground renewal 533,000

00:22:40.839 --> 00:22:43.119
it's

00:22:43.200 --> 00:22:46.400
not oned through you Mr Mayor it's not

00:22:46.480 --> 00:22:48.400
tied to a specific playground right

00:22:48.480 --> 00:22:50.200
there are renewals across playgrounds

00:22:50.279 --> 00:22:52.599
right across the scope so it's not tied

00:22:52.680 --> 00:22:55.000
to a specific one in that particular one

00:22:55.079 --> 00:22:56.920
it's renewals that are required to the

00:22:57.000 --> 00:22:59.400
playgrounds and that has been allocated

00:22:59.480 --> 00:23:02.279
to allow us to do that based on on our

00:23:02.359 --> 00:23:04.319
inspection regime it's not tied to a

00:23:04.400 --> 00:23:07.559
specific playground so other words bits

00:23:07.640 --> 00:23:09.240
of equipment yeah so in other words it's

00:23:09.319 --> 00:23:11.599
just renewal stuff

00:23:11.680 --> 00:23:14.319
for yes maintenance let's call it right

00:23:14.400 --> 00:23:17.119
regarding  so the other one here is

00:23:17.200 --> 00:23:18.599
Coastal accessibility program the

00:23:18.680 --> 00:23:21.079
planning and concept

00:23:21.160 --> 00:23:24.519
development  sorry if I'm not up to

00:23:24.599 --> 00:23:26.759
speed with the accessibility projects I

00:23:26.839 --> 00:23:29.160
know one of them was Spencer there was

00:23:29.240 --> 00:23:31.680
three that was part of a a trio again

00:23:31.759 --> 00:23:35.000
was it the coastal accessibility

00:23:36.000 --> 00:23:38.000
program I think there were three I can't

00:23:38.079 --> 00:23:40.880
remember which ones  we currently on

00:23:40.960 --> 00:23:42.599
at the moment now I can take that on

00:23:42.680 --> 00:23:44.559
notice and get back to on those the

00:23:44.640 --> 00:23:46.440
coastal accessibility again this is seed

00:23:46.519 --> 00:23:48.519
money that we've got back into the

00:23:48.599 --> 00:23:51.480
program which is why we got it to do the

00:23:51.559 --> 00:23:54.359
works in order to Leverage The the rest

00:23:54.440 --> 00:23:56.759
of the funding to do the the coastal

00:23:56.839 --> 00:24:00.440
accessibility pieces

00:24:01.319 --> 00:24:04.480
can three miss one off the top of my

00:24:04.559 --> 00:24:07.319
head of those was kakora Beach down in

00:24:07.400 --> 00:24:08.759
Eden too that we were looking at as part

00:24:08.839 --> 00:24:11.240
of that as

00:24:13.359 --> 00:24:17.920
well  and  I've got foot so kakora

00:24:18.000 --> 00:24:19.559
spenter park and there must be one more

00:24:19.640 --> 00:24:20.960
that I can't think of off the top of my

00:24:21.039 --> 00:24:24.519
head  foot paths so I've got cycleway

00:24:24.599 --> 00:24:27.960
renewal and path renewal  so they're

00:24:28.039 --> 00:24:31.000
renew they're not new Pathways can I ask

00:24:31.079 --> 00:24:35.599
is that T I think it was included in

00:24:35.680 --> 00:24:37.519
that we haven't spent money on footpaths

00:24:37.599 --> 00:24:40.000
for a while so just curious about

00:24:40.079 --> 00:24:43.799
400,000 there through you Mr M as you're

00:24:43.880 --> 00:24:45.079
aware we're going through the active

00:24:45.160 --> 00:24:46.680
transport strategy at the moment the

00:24:46.759 --> 00:24:49.599
strategy that will then deliver the

00:24:49.680 --> 00:24:51.240
priorities for which paths we're going

00:24:51.319 --> 00:24:53.440
to repair  that's where that's tied

00:24:53.519 --> 00:24:55.119
into it so we know when we have the

00:24:55.200 --> 00:24:57.240
active transport strategy completed we

00:24:57.319 --> 00:24:59.039
will have a number of Pathways that then

00:24:59.119 --> 00:25:01.319
be prioritized  and you're exactly

00:25:01.400 --> 00:25:03.640
right we haven't invested a lot in paths

00:25:03.720 --> 00:25:05.559
in the future hence the reason we ring

00:25:05.640 --> 00:25:07.680
fence in the past hence the reason we

00:25:07.759 --> 00:25:11.039
bring fenced money  to action the

00:25:11.119 --> 00:25:14.599
outcomes of the active transport

00:25:14.680 --> 00:25:17.599
strategy so yeah so we haven't yet

00:25:17.680 --> 00:25:19.559
decided where that 400,000 is going it's

00:25:19.640 --> 00:25:20.920
just a quarantined amount of money for

00:25:21.000 --> 00:25:23.279
footpaths at this point in time through

00:25:23.359 --> 00:25:26.400
you Mr Mayor that's that's the idea of it

00:25:26.480 --> 00:25:28.799
we have good idea but we we're not going

00:25:28.880 --> 00:25:30.640
to go firm until we get the results of

00:25:30.720 --> 00:25:32.920
the

00:25:33.599 --> 00:25:36.960
strategy Mr Mayor just to reinforce a key

00:25:37.039 --> 00:25:38.599
Point here that the focus will be on

00:25:38.680 --> 00:25:40.920
renewing what we've got that needs to be

00:25:41.000 --> 00:25:42.880
renewed rather than building new things

00:25:42.960 --> 00:25:46.160
because if you look at our cycleway and

00:25:46.240 --> 00:25:48.000
footpath network across the sh there are

00:25:48.079 --> 00:25:51.400
a number of areas that do need renewing

00:25:51.480 --> 00:25:53.119
and starting to pose the risk if we

00:25:53.200 --> 00:25:54.680
don't renew them so so rather than

00:25:54.759 --> 00:25:56.039
asse that's going to go to new things

00:25:56.119 --> 00:25:57.920
it's more than likely going to be fixing

00:25:58.000 --> 00:25:59.359
what we

00:25:59.440 --> 00:26:01.359
 I agree Mr CEO and I think that

00:26:01.440 --> 00:26:02.960
that's good I it would just be good for

00:26:03.039 --> 00:26:04.960
councilors to have a heads up as to what

00:26:05.039 --> 00:26:06.519
that  I mean she's not here at the

00:26:06.599 --> 00:26:07.640
moment but lovees talking about

00:26:07.720 --> 00:26:09.519
priorities I think she's right in this

00:26:09.599 --> 00:26:11.200
instance I'd like to see the active

00:26:11.279 --> 00:26:14.680
transport strategy as to you why there's

00:26:14.759 --> 00:26:17.279
one and a two and a three and  so I've

00:26:17.359 --> 00:26:20.119
got a carpet replacement  carpet

00:26:20.200 --> 00:26:23.279
replacement here in the BB Triple C for

00:26:23.359 --> 00:26:26.160
115,000 is that

00:26:26.240 --> 00:26:28.680
right that's right okay

00:26:28.759 --> 00:26:33.039
looks pretty good but I mean

00:26:33.119 --> 00:26:34.559
we

00:26:34.640 --> 00:26:38.319
115,000 only nly  I've also got chura

00:26:38.400 --> 00:26:41.039
Community Center chura Library so is

00:26:41.119 --> 00:26:43.039
this the

00:26:43.119 --> 00:26:46.119
$440,000 so it does say reserve funds so

00:26:46.200 --> 00:26:49.839
is that for the renovations downstairs

00:26:49.920 --> 00:26:53.799
and did we lock that in I can't remember

00:26:53.880 --> 00:26:55.799
because we talked about activating it I

00:26:55.880 --> 00:26:58.880
didn't know that it was a a a done deal

00:26:58.960 --> 00:27:02.440
yet but you can explain

00:27:05.000 --> 00:27:07.119
that that it was actually an old

00:27:07.200 --> 00:27:08.720
resolution of council to move forward

00:27:08.799 --> 00:27:12.200
with this to get a  da done which has

00:27:12.279 --> 00:27:14.440
now been done and this is to get the

00:27:14.519 --> 00:27:16.359
works

00:27:16.440 --> 00:27:18.680
happening yeah that's what's is in

00:27:18.759 --> 00:27:20.359
what's the how we activating it it's

00:27:20.440 --> 00:27:23.119
just turning into store rooms is it I'm

00:27:23.200 --> 00:27:25.440
going to be leased out I remember there

00:27:25.519 --> 00:27:27.759
being some kind of a strategy to recover

00:27:27.839 --> 00:27:28.839
funds

00:27:28.920 --> 00:27:31.960
yeah yeah so Miss Mayor the intention was

00:27:32.039 --> 00:27:34.079
to turn it into a leasable space

00:27:34.160 --> 00:27:36.440
predominantly leasable space with some

00:27:36.519 --> 00:27:38.240
of the area a little bit flexible as to

00:27:38.319 --> 00:27:39.960
whether it could be leased out or

00:27:40.039 --> 00:27:42.839
utilized for  supporting Council

00:27:42.920 --> 00:27:46.359
services in the library and  some as

00:27:46.440 --> 00:27:48.000
in some additional meeting and office

00:27:48.079 --> 00:27:50.720
space there so that was where Council

00:27:50.799 --> 00:27:53.680
ended up resolving in the end  the

00:27:53.759 --> 00:27:56.079
concepts that were put to

00:27:56.160 --> 00:27:59.400
council didn't necessarily

00:27:59.480 --> 00:28:02.200
initially have the level of flexibility

00:28:02.279 --> 00:28:03.200
to

00:28:03.279 --> 00:28:06.079
lease as much as Council wanted so that

00:28:06.160 --> 00:28:07.680
got changed in the day got lodged on

00:28:07.759 --> 00:28:08.880
that

00:28:08.960 --> 00:28:12.720
basis yeah is that is that 440 is that a

00:28:12.799 --> 00:28:14.480
quote that you've got from a builder or

00:28:14.559 --> 00:28:17.440
is that  is that just an estimate

00:28:17.519 --> 00:28:19.759
internally yeah my understanding is that

00:28:19.839 --> 00:28:21.599
that estimate was developed on unit

00:28:21.680 --> 00:28:25.759
rates from  yeah the construction

00:28:25.839 --> 00:28:28.000
indexes that you get access to not from

00:28:28.079 --> 00:28:30.680
from a market quite yet certainly not

00:28:30.759 --> 00:28:33.440
yeah and that's that's one of the issues

00:28:33.519 --> 00:28:34.799
we do have in local government is we

00:28:34.880 --> 00:28:36.960
can't go to the market and ask the

00:28:37.039 --> 00:28:38.720
market to price things unless we have a

00:28:38.799 --> 00:28:41.319
budget committed to say that we intend

00:28:41.400 --> 00:28:44.440
to do it and yeah that is a limitation

00:28:44.519 --> 00:28:47.440
of the system we work in no absolutely I

00:28:47.519 --> 00:28:49.640
just  you know is there contingency

00:28:49.720 --> 00:28:51.480
built into that because I mean I just

00:28:51.559 --> 00:28:54.400
say we we we've had a few projects

00:28:54.480 --> 00:28:55.920
recently that have gone significantly

00:28:56.000 --> 00:28:57.599
over budget and so I'm just wondering if

00:28:57.680 --> 00:28:59.960
400 40 turns into 650 halfway through

00:29:00.039 --> 00:29:02.480
the project it's REM Mr me that's a fair

00:29:02.559 --> 00:29:04.680
question and in this instance I'm given

00:29:04.759 --> 00:29:06.680
I'd say this is not a core community

00:29:06.759 --> 00:29:08.240
service that council's talking about

00:29:08.319 --> 00:29:11.640
here if we went to Market and got prices

00:29:11.720 --> 00:29:13.160
back that essentially blew the whole

00:29:13.240 --> 00:29:15.000
business case around getting a return on

00:29:15.079 --> 00:29:16.359
the investment to do the work in the

00:29:16.440 --> 00:29:18.480
first place then we probably wouldn't

00:29:18.559 --> 00:29:21.039
recommend to proceed with it but this is

00:29:21.119 --> 00:29:22.759
the indicative figure we think we start

00:29:22.839 --> 00:29:24.119
with and then eventually we'll go to the

00:29:24.200 --> 00:29:25.839
market and then we'll provide a report

00:29:25.920 --> 00:29:27.720
on on it afterwards and idea the other

00:29:27.799 --> 00:29:29.680
thing to keep in in mind with this

00:29:29.759 --> 00:29:32.440
particular space is we fully expect that

00:29:32.519 --> 00:29:34.039
Council will come under pressure down

00:29:34.119 --> 00:29:36.000
the track from Community organ

00:29:36.079 --> 00:29:37.960
organizations to lease the space at a

00:29:38.039 --> 00:29:39.440
subsidized rate which then might

00:29:39.519 --> 00:29:40.720
undermine the investment in the first

00:29:40.799 --> 00:29:43.359
place so we'll get to that

00:29:43.440 --> 00:29:46.200
eventually through you m de sorry if I

00:29:46.279 --> 00:29:48.440
can add to that just the last Council

00:29:48.519 --> 00:29:51.200
resolution the next step in that is for

00:29:51.279 --> 00:29:53.519
us to run an eoi process so before we

00:29:53.599 --> 00:29:55.680
commit any of that money to run AI

00:29:55.759 --> 00:29:56.960
process to see if there is interest in

00:29:57.039 --> 00:29:58.720
the market to take up that leasable

00:29:58.799 --> 00:30:00.559
space so there's still a few more steps

00:30:00.640 --> 00:30:02.519
before we go and spend that

00:30:02.599 --> 00:30:05.799
money  you've got just underneath that

00:30:05.880 --> 00:30:08.680
 is

00:30:10.039 --> 00:30:12.759
$475,000 for the Youth space renewal is

00:30:12.839 --> 00:30:17.759
that that building there and why sorry

00:30:17.839 --> 00:30:20.200
if my memory serves me poorly because I

00:30:20.279 --> 00:30:22.480
thought that that was a 1801 you know

00:30:22.559 --> 00:30:25.119
171 180,000 job not a half a million

00:30:25.200 --> 00:30:28.680
dollar job three no Reserve funds 175

00:30:28.759 --> 00:30:30.599
Revenue funds so in other words from the

00:30:30.680 --> 00:30:34.359
Grant from the  general fund this year

00:30:34.440 --> 00:30:37.799
$300,000 is that

00:30:45.359 --> 00:30:49.000
right oh same page just right just Ben

00:30:49.079 --> 00:30:51.599
Library 124 which is

00:30:51.680 --> 00:30:55.680
p get

00:31:13.200 --> 00:31:15.160
Mr M I might have to take on notice what

00:31:15.240 --> 00:31:18.079
the scope of that actually included 

00:31:18.160 --> 00:31:19.359
what I do

00:31:19.440 --> 00:31:22.079
know no through M you know it was

00:31:22.160 --> 00:31:24.559
definitely  the scope was definitely

00:31:24.640 --> 00:31:26.119
more complex than that we did actually

00:31:26.200 --> 00:31:28.000
get a comprehensive safety order to of

00:31:28.079 --> 00:31:29.480
that building done that said it's got

00:31:29.559 --> 00:31:31.200
some serious limitations if it wants to

00:31:31.279 --> 00:31:34.720
be utilized for anything functional so

00:31:34.799 --> 00:31:36.839
it's a little bit more complicated ask

00:31:36.920 --> 00:31:37.640
the

00:31:37.720 --> 00:31:40.960
director through you Mr M  that's the

00:31:41.039 --> 00:31:44.480
case  the money was out allocated

00:31:44.559 --> 00:31:47.519
because we carried out that  detailed

00:31:47.599 --> 00:31:50.039
inspection we detected cracking to the

00:31:50.119 --> 00:31:51.799
external masonry and subsidence to the

00:31:51.880 --> 00:31:54.200
internal floor frame to the northeastern

00:31:54.279 --> 00:31:56.119
front corner of the building we got

00:31:56.200 --> 00:31:58.519
moisture getting through transferring

00:31:58.599 --> 00:32:00.319
through the external mry into the brick

00:32:00.400 --> 00:32:03.640
work and the mortar and plaster work was

00:32:03.720 --> 00:32:06.319
decaying deterioration of the glazing

00:32:06.400 --> 00:32:08.640
and the the original double hung Timber

00:32:08.720 --> 00:32:11.319
Windows which are all now  rotting

00:32:11.400 --> 00:32:14.160
away in there we've got dry rots in the

00:32:14.240 --> 00:32:16.480
internals the ballustrade Rings and the

00:32:16.559 --> 00:32:19.559
chimney  there is quite substantial

00:32:19.640 --> 00:32:21.799
amounts of work in there hence the

00:32:21.880 --> 00:32:24.680
reason there's full scope of work to be

00:32:24.759 --> 00:32:26.960
done if we are to refurbish that to a

00:32:27.039 --> 00:32:29.359
standard  that's it so that's why that

00:32:29.440 --> 00:32:32.079
has been put

00:32:32.359 --> 00:32:35.039
together I have the I have the

00:32:35.119 --> 00:32:36.960
report oh so it's going to come to a

00:32:37.039 --> 00:32:39.759
council me cheating or is this the

00:32:39.839 --> 00:32:41.680
report is this is the the approval here

00:32:41.759 --> 00:32:44.119
the budget for it  and if so can you

00:32:44.200 --> 00:32:46.519
just expand is that building that's a

00:32:46.599 --> 00:32:48.759
that's Community Land so it can't be

00:32:48.839 --> 00:32:51.000
sold

00:32:51.079 --> 00:32:53.400
 to I mean what other options are

00:32:53.480 --> 00:32:54.680
there I mean to do nothing and just lock

00:32:54.759 --> 00:32:59.799
the doors we can't build those

00:33:00.960 --> 00:33:02.599
is that well that's the question is it

00:33:02.680 --> 00:33:05.279
Heritage I mean that's a huge amount of

00:33:05.359 --> 00:33:08.279
money that's a brand new

00:33:10.279 --> 00:33:13.000
house just that I do remember that we

00:33:13.079 --> 00:33:15.279
had a council report on that and a

00:33:15.359 --> 00:33:17.960
decision  perhaps and that did go into

00:33:18.039 --> 00:33:19.400
I understand some of those Heritage

00:33:19.480 --> 00:33:22.119
issues and what was

00:33:22.200 --> 00:33:24.160
happening through you Mr Mayor that's

00:33:24.240 --> 00:33:27.319
correct we did bring this to council and

00:33:27.400 --> 00:33:29.200
explain the issues in that space there

00:33:29.279 --> 00:33:30.599
are Heritage issues it's within the

00:33:30.680 --> 00:33:33.000
Heritage Precinct there's obviously 

00:33:33.079 --> 00:33:34.359
you know we've got Heritage foot path

00:33:34.440 --> 00:33:36.440
out the front as you're aware the the KB

00:33:36.519 --> 00:33:38.119
and gutter and it is linked

00:33:38.200 --> 00:33:40.680
intrinsically to that space  it's it's

00:33:40.759 --> 00:33:42.920
not an easy piece of work to do 

00:33:43.000 --> 00:33:44.680
initially when we first brought it we

00:33:44.759 --> 00:33:45.680
thought it was just going to be a look

00:33:45.759 --> 00:33:46.759
and a promise that we were going to go

00:33:46.839 --> 00:33:48.960
and do to do exactly that to activate

00:33:49.039 --> 00:33:52.039
the space however because of the types

00:33:52.119 --> 00:33:54.480
of people using it  and we're looking

00:33:54.559 --> 00:33:56.200
at putting youth or vulnerable groups in

00:33:56.279 --> 00:33:58.480
there we can't do it in an unsafe manner

00:33:58.559 --> 00:33:59.720
hence the reason we've done a more

00:33:59.799 --> 00:34:01.559
comprehensive inspection which has led

00:34:01.640 --> 00:34:05.119
to this number  it has not been fully

00:34:05.200 --> 00:34:07.480
scoped yet so we haven't got a Builders

00:34:07.559 --> 00:34:09.079
this is what it will cost This Is Us

00:34:09.159 --> 00:34:11.119
doing our due diligence and thinking

00:34:11.199 --> 00:34:14.079
that's how much it will

00:34:14.159 --> 00:34:17.199
cost  thank you I mean something like

00:34:17.280 --> 00:34:19.840
this like considering our limitations on

00:34:19.920 --> 00:34:21.440
our budget at the moment is something

00:34:21.519 --> 00:34:23.199
like this just in off the top of your

00:34:23.280 --> 00:34:27.199
head Mr CEO grant funding available for

00:34:27.280 --> 00:34:29.360
for things like this or even the library

00:34:29.440 --> 00:34:32.239
I mean there's of capital spend

00:34:32.320 --> 00:34:34.800
there  is that something and I'm not

00:34:34.880 --> 00:34:36.000
saying that it doesn't need to be done

00:34:36.079 --> 00:34:38.639
like I'd love to go plate everything but

00:34:38.719 --> 00:34:40.719
 is it something we could hang around

00:34:40.800 --> 00:34:42.320
and wait there's no desperation for it

00:34:42.400 --> 00:34:44.199
and look for grant funding

00:34:44.280 --> 00:34:46.599
instead Mr we have applied for grants

00:34:46.679 --> 00:34:49.039
for that in the past I can't remember

00:34:49.119 --> 00:34:53.079
the scale and the response that we reive

00:34:53.159 --> 00:34:55.760
but I I'd be happy to bring back some

00:34:55.840 --> 00:34:57.960
further details on that particular item

00:34:58.039 --> 00:35:00.440
when we do bring the final budget back

00:35:00.519 --> 00:35:03.639
on what we've done in the past and how

00:35:03.719 --> 00:35:05.760
we've got to this scope as

00:35:05.840 --> 00:35:09.199
well any CH I just wanted to make a

00:35:09.280 --> 00:35:13.280
comment included in that b74 is 175,000

00:35:13.360 --> 00:35:15.840
that has been carried taken out of our Q

00:35:15.920 --> 00:35:19.000
our 24 budget and moved into fy2 to help

00:35:19.079 --> 00:35:21.239
the the original budget yes so that

00:35:21.320 --> 00:35:23.880
hasn't that work as they decided to do

00:35:23.960 --> 00:35:25.599
that work they found we needed more so

00:35:25.679 --> 00:35:30.239
it's been moved into fi25 move from

00:35:30.599 --> 00:35:33.599
fy4

00:35:34.880 --> 00:35:37.000
cancel I have a couple of questions and

00:35:37.079 --> 00:35:38.599
it relates around our long-term

00:35:38.679 --> 00:35:41.239
financial plan and option b being I

00:35:41.320 --> 00:35:43.119
realiz staff are recommending option A

00:35:43.199 --> 00:35:46.440
and option b is our current course of

00:35:46.519 --> 00:35:50.599
trajectory in the 27 if we go to page I

00:35:50.679 --> 00:35:53.159
think it's page 29 of the long-term

00:35:53.239 --> 00:35:55.760
financial

00:35:56.320 --> 00:36:00.000
plan which is the cash flow and

00:36:00.079 --> 00:36:02.880
also yeah I think it's 20 of the actual

00:36:02.960 --> 00:36:05.360
report so on that

00:36:05.440 --> 00:36:08.079
we on on one part option b our

00:36:08.159 --> 00:36:10.960
depreciation modelization in

00:36:11.039 --> 00:36:14.199
2728 is 26 million then we goes to 27

00:36:14.280 --> 00:36:16.480
million 28 29 and continues on a

00:36:16.559 --> 00:36:19.000
projectory up to 32 million if I go to

00:36:19.079 --> 00:36:20.519
our assets and the purchase of

00:36:20.599 --> 00:36:22.159
infrastructure property plan equipment

00:36:22.239 --> 00:36:24.440
which I say our asset renewals are

00:36:24.519 --> 00:36:28.039
actually under  our spend is less than

00:36:28.119 --> 00:36:30.039
what our depreciation is so we'd be

00:36:30.119 --> 00:36:32.360
actually living off depreciation from

00:36:32.440 --> 00:36:35.320
2728 onwards if I read that right could

00:36:35.400 --> 00:36:36.760
that be

00:36:36.840 --> 00:36:39.159
clarified yeah through Mr Mayor what

00:36:39.239 --> 00:36:40.679
you're alluding to there is the fact

00:36:40.760 --> 00:36:42.159
that in the early years of this current

00:36:42.239 --> 00:36:44.400
long-term financial plan model I would

00:36:44.480 --> 00:36:47.800
describe it as we are spending adequate

00:36:47.880 --> 00:36:49.920
funds to do the renewals we need to do

00:36:50.000 --> 00:36:51.280
as well as picking up some of the

00:36:51.360 --> 00:36:53.960
backlog Ren the things we haven't got to

00:36:54.039 --> 00:36:56.679
yet but then in future years we start to

00:36:56.760 --> 00:36:58.800
get to the point where where we're

00:36:58.880 --> 00:37:00.519
assing an underspend on average

00:37:00.599 --> 00:37:01.880
compared to what we should be each year

00:37:01.960 --> 00:37:03.719
to look after the assets we've got and

00:37:03.800 --> 00:37:05.480
that is certainly concerning and it's

00:37:05.559 --> 00:37:07.880
also reflected if you look at the

00:37:07.960 --> 00:37:10.559
 the asset renewal ratio and our

00:37:10.639 --> 00:37:12.159
ratios are included in there I think you

00:37:12.239 --> 00:37:13.679
see three or four years of green dots

00:37:13.760 --> 00:37:15.880
and then they pretty quickly turn red

00:37:15.960 --> 00:37:19.519
dots that are declining significantly so

00:37:19.599 --> 00:37:21.679
 you could say that this long-term

00:37:21.760 --> 00:37:23.119
financial

00:37:23.199 --> 00:37:28.360
plan doesn't necessarily highlight

00:37:28.440 --> 00:37:30.239
and I'll be very Frank this doesn't

00:37:30.320 --> 00:37:31.800
highlight the risk of an increasing

00:37:31.880 --> 00:37:33.239
maintenance burden because we're not

00:37:33.320 --> 00:37:35.880
spending enough on renewal so if we if

00:37:35.960 --> 00:37:39.239
we did this I would say not too far out

00:37:39.320 --> 00:37:41.400
of outside of the 10year period we'd

00:37:41.480 --> 00:37:44.239
start to see decreasing service levels

00:37:44.320 --> 00:37:46.039
across the assets that we looked after

00:37:46.119 --> 00:37:47.960
so in other words things like more

00:37:48.039 --> 00:37:49.519
potholes on the roads because we aren't

00:37:49.599 --> 00:37:51.159
spending enough ceiling when we should

00:37:51.239 --> 00:37:54.159
be or  reconstructing Pavements when

00:37:54.239 --> 00:37:55.519
we should be

00:37:55.599 --> 00:37:58.400
so even under that model

00:37:58.480 --> 00:37:59.760
that doesn't show that we're running out

00:37:59.840 --> 00:38:01.559
of cash over the life but we're

00:38:01.639 --> 00:38:03.239
essentially not spending enough to do

00:38:03.320 --> 00:38:05.159
everything we should be which is it is a

00:38:05.239 --> 00:38:06.679
concern should be of concern to

00:38:06.760 --> 00:38:09.679
counselors and in option C when we have

00:38:09.760 --> 00:38:11.639
a look at the cash flow statement it

00:38:11.719 --> 00:38:13.719
shows that we'll be out of cash

00:38:13.800 --> 00:38:17.000
somewhere between 25 26 if we went with

00:38:17.079 --> 00:38:18.960
option C and not took up the next lot

00:38:19.039 --> 00:38:22.639
rate B me Mr Mayor that's correct if we

00:38:22.719 --> 00:38:24.360
don't

00:38:24.440 --> 00:38:26.960
 we've explained this not yet publicly

00:38:27.039 --> 00:38:28.960
but if we don't take up the second year

00:38:29.039 --> 00:38:32.320
of the SRV will run out of cash even

00:38:32.400 --> 00:38:34.159
quicker than was originally project

00:38:34.239 --> 00:38:36.199
projected when the the SRV was first

00:38:36.280 --> 00:38:38.639
applied for and the main reason for that

00:38:38.719 --> 00:38:40.880
is that costs have escalated far more

00:38:40.960 --> 00:38:42.840
quickly than what our original models

00:38:42.920 --> 00:38:45.400
assed when we put them together so

00:38:45.480 --> 00:38:47.360
we're already heading backwards and if

00:38:47.440 --> 00:38:50.599
 if Council doesn't move forward with

00:38:50.679 --> 00:38:52.079
the increasing rates as a previously

00:38:52.159 --> 00:38:53.639
planned to then yes there is a serious

00:38:53.719 --> 00:38:56.440
risk will run out of cash very quickly

00:38:56.519 --> 00:38:58.360
 Mr Mayor just to add on to that

00:38:58.440 --> 00:38:59.719
question could you just take us to in

00:38:59.800 --> 00:39:01.639
the Strategic Asset Management plan

00:39:01.719 --> 00:39:03.599
you've actually outlined some of the the

00:39:03.679 --> 00:39:05.800
shortfalls to

00:39:05.880 --> 00:39:09.039
maintain  services and  I'm thinking

00:39:09.119 --> 00:39:12.159
of  down the back of what doesn't even

00:39:12.239 --> 00:39:13.639
have page numbers but you you've got

00:39:13.719 --> 00:39:16.400
building assets management plan you go

00:39:16.480 --> 00:39:18.719
roads Asset Management plan the roads

00:39:18.800 --> 00:39:20.199
yes and then that that you've actually

00:39:20.280 --> 00:39:24.039
outlined some of the shortfall

00:39:28.000 --> 00:39:30.039
I'm sorry I haven't got precise

00:39:30.119 --> 00:39:32.280
page

00:39:32.360 --> 00:39:36.880
microphone yes so Mr M even the the

00:39:36.960 --> 00:39:38.719
long-term financial plan that Council

00:39:38.800 --> 00:39:40.719
adopted in applying for the SRV we made

00:39:40.800 --> 00:39:45.079
this quite clear had  a in Broad terms

00:39:45.159 --> 00:39:48.719
roughly 50% underspend in the transport

00:39:48.800 --> 00:39:52.519
area so roads and bridges on renewals

00:39:52.599 --> 00:39:53.960
relative to what it should be so in

00:39:54.039 --> 00:39:56.920
other words even with the SRV we still

00:39:57.000 --> 00:39:58.599
only spending half of what we should be

00:39:58.679 --> 00:40:00.320
which reflects what I just said about

00:40:00.400 --> 00:40:02.039
that  if you get at the back end of

00:40:02.119 --> 00:40:04.920
this current plan we don't run out of

00:40:05.000 --> 00:40:06.519
cash but that's because we're assing

00:40:06.599 --> 00:40:08.079
we're going to only spend half as much

00:40:08.159 --> 00:40:10.239
as what we really need to in our asset

00:40:10.320 --> 00:40:13.840
plans and I know you sort of pointed to

00:40:13.920 --> 00:40:16.039
buildings that's an example of where it

00:40:16.119 --> 00:40:18.159
occurs but it's not as material as in

00:40:18.239 --> 00:40:19.760
the Road and Bridge Network where the

00:40:19.840 --> 00:40:21.519
big dollars are they they make up most

00:40:21.599 --> 00:40:23.800
of our depreciation expense in our asset

00:40:23.880 --> 00:40:24.800
base I think

00:40:24.880 --> 00:40:28.199
it's 700 million or something out of

00:40:28.280 --> 00:40:30.119
that asset base off the top of

00:40:30.199 --> 00:40:32.559
my well one one more quick question on

00:40:32.639 --> 00:40:33.760
that you've got a 10year average

00:40:33.840 --> 00:40:37.599
shortfall per year in roads of nearly 7

00:40:37.679 --> 00:40:40.119
million is that on current dollars will

00:40:40.199 --> 00:40:42.880
that go up every

00:40:42.960 --> 00:40:45.360
year yes so through Mr Mayor that's all

00:40:45.440 --> 00:40:48.719
it's all calculated in today's term so

00:40:48.800 --> 00:40:51.880
again  whether that Gap goes up is

00:40:51.960 --> 00:40:54.559
partially dependent on where our income

00:40:54.639 --> 00:40:58.039
again  increases at at a lower than

00:40:58.119 --> 00:41:00.159
the cost of looking after roads goes up

00:41:00.239 --> 00:41:02.519
which is as we've explained is typically

00:41:02.599 --> 00:41:05.039
what happens that I part of

00:41:05.119 --> 00:41:06.440
traditionally set the rate Peg at a

00:41:06.519 --> 00:41:08.119
lower amount than what construction

00:41:08.199 --> 00:41:10.519
indexes have gone up by and in Rural and

00:41:10.599 --> 00:41:12.679
Regional areas most of our expenses are

00:41:12.760 --> 00:41:15.360
in asset Based Services roads Bridges

00:41:15.440 --> 00:41:16.920
and they tend to go up by more than what

00:41:17.000 --> 00:41:19.599
a typical local government basket of

00:41:19.679 --> 00:41:22.920
goods does I part have at least  just

00:41:23.000 --> 00:41:24.960
now reviewed their methodology to start

00:41:25.039 --> 00:41:26.800
to take that sort of thing into account

00:41:26.880 --> 00:41:29.599
but we don't know  yet it's too early

00:41:29.679 --> 00:41:31.920
to tell if future rate pegs will be more

00:41:32.000 --> 00:41:34.239
reflective of what we see the cost go up

00:41:34.320 --> 00:41:36.199
buying building

00:41:36.280 --> 00:41:40.519
roads yes yeah so thank you for  so

00:41:40.599 --> 00:41:42.480
going into this so the roads Asset

00:41:42.559 --> 00:41:44.320
Management plan so you can see option A

00:41:44.400 --> 00:41:46.840
B and C so we actually what we need to

00:41:46.920 --> 00:41:51.480
spend every year on roads is 20.7

00:41:51.559 --> 00:41:55.320
million option b says we'll spend $13.7

00:41:55.400 --> 00:41:58.039
million which is 66%

00:41:58.119 --> 00:42:00.320
 of our asset management plan for

00:42:00.400 --> 00:42:03.639
roads and then that's still I would say

00:42:03.719 --> 00:42:05.920
significantly but it's still better than

00:42:06.000 --> 00:42:06.679
the

00:42:06.760 --> 00:42:11.159
57.82 per or 11 so12 million let's say

00:42:11.239 --> 00:42:13.400
so with an extra

00:42:13.480 --> 00:42:14.880
[Music]

00:42:14.960 --> 00:42:16.639
11.5 actually I don't know what it is

00:42:16.719 --> 00:42:18.800
off the top of my head  over the

00:42:18.880 --> 00:42:22.679
two years of SRV

00:42:22.760 --> 00:42:27.639
increase we will be putting an extra

00:42:27.719 --> 00:42:29.360
$1.8

00:42:29.440 --> 00:42:33.159
million a year into roads and it's nice

00:42:33.239 --> 00:42:34.679
to be able to see this but can I just

00:42:34.760 --> 00:42:35.679
have the

00:42:35.760 --> 00:42:38.000
confirmed well no I'm just trying based

00:42:38.079 --> 00:42:39.320
on these figures because you can see so

00:42:39.400 --> 00:42:43.840
it's 13.7 there 11.9 rate Peg

00:42:43.920 --> 00:42:46.440
only  so I'm just trying to work that

00:42:46.519 --> 00:42:49.199
out is that

00:42:51.039 --> 00:42:56.119
right  just option C is rate Peg from

00:42:56.199 --> 00:42:59.239
25 on W we've already adopted and

00:42:59.320 --> 00:43:02.719
approved and and done the 24% so it's

00:43:02.800 --> 00:43:06.280
not the full SRV difference in that

00:43:06.360 --> 00:43:08.400
space

00:43:08.480 --> 00:43:12.519
 but yes that's part of that

00:43:12.599 --> 00:43:15.320
19.6% yeah I say because like just put

00:43:15.400 --> 00:43:16.440
to what the Mayor was saying before

00:43:16.519 --> 00:43:18.400
we'll be living off depreciation from 25

00:43:18.480 --> 00:43:22.119
26 we're living off depreciation now 

00:43:22.199 --> 00:43:24.440
and I just like it's one of the things

00:43:24.519 --> 00:43:25.840
that I said during the when we're

00:43:25.920 --> 00:43:28.679
adopting the SIV is

00:43:28.760 --> 00:43:32.519
how how you the the formula whatever you

00:43:32.599 --> 00:43:35.239
want to call it came to getting this

00:43:35.320 --> 00:43:36.880
much money and allocating just that much

00:43:36.960 --> 00:43:38.920
to roads and that much to and that much

00:43:39.000 --> 00:43:42.440
to you know is is this is this something

00:43:42.519 --> 00:43:46.840
that can still be played with in that

00:43:46.920 --> 00:43:49.639
space three Mr mer it certainly can be

00:43:49.719 --> 00:43:52.480
and I'll  actually go back to a

00:43:52.559 --> 00:43:53.920
question that councilor Porter asked

00:43:54.000 --> 00:43:55.360
earlier around what has changed out of

00:43:55.440 --> 00:43:58.440
service level reviews and

00:43:58.519 --> 00:43:59.960
again we've prepared information that

00:44:00.039 --> 00:44:02.480
we've provided to councilors on  what

00:44:02.559 --> 00:44:06.239
services cost what  if changes were

00:44:06.320 --> 00:44:09.039
going to be made what the potential

00:44:09.119 --> 00:44:10.880
savings could be and then some

00:44:10.960 --> 00:44:13.360
information on the impacts of that and

00:44:13.440 --> 00:44:14.960
when Council paor asked his question I

00:44:15.039 --> 00:44:17.280
said nothing that's that

00:44:17.360 --> 00:44:19.360
material the underlying issue is the

00:44:19.440 --> 00:44:20.800
scale of the asset base we've got in

00:44:20.880 --> 00:44:22.480
roads and bridges and it doesn't matter

00:44:22.559 --> 00:44:24.320
what we do in a lot of other places it's

00:44:24.400 --> 00:44:26.000
never going to get us close to the

00:44:26.079 --> 00:44:28.119
materiality level need to make the

00:44:28.199 --> 00:44:29.800
change we need and the reason these

00:44:29.880 --> 00:44:31.320
plant were put

00:44:31.400 --> 00:44:35.639
together the way they were was that

00:44:35.719 --> 00:44:38.480
roads and bridges

00:44:38.559 --> 00:44:41.559
 roads in particular if we don't spend

00:44:41.639 --> 00:44:43.880
on them we ar going to wear the

00:44:43.960 --> 00:44:46.079
consequences right now it won't be till

00:44:46.159 --> 00:44:48.440
5 to 10 years down the track so this

00:44:48.519 --> 00:44:50.880
model essentially bought this Council

00:44:50.960 --> 00:44:53.920
and the next Council a bit of time to

00:44:54.000 --> 00:44:56.480
make some really really tough decisions

00:44:56.559 --> 00:44:57.719
and and

00:44:57.800 --> 00:44:59.360
we know that and we've articulated that

00:44:59.440 --> 00:45:01.880
before so this this isn't a sustainable

00:45:01.960 --> 00:45:03.719
model certainly the one that we are

00:45:03.800 --> 00:45:06.159
under even if you move forward with the

00:45:06.239 --> 00:45:09.719
second year of the approved SRV is not a

00:45:09.800 --> 00:45:12.480
sustainable model in the long term 

00:45:12.559 --> 00:45:15.079
can I just recall back to a workshop

00:45:15.159 --> 00:45:17.320
that we had either a week or two ago and

00:45:17.400 --> 00:45:20.800
you had that great slide of  where the

00:45:20.880 --> 00:45:26.000
allocation of that additional six 6.5

00:45:26.079 --> 00:45:29.880
million was and it was it was it was

00:45:29.960 --> 00:45:34.360
good and I I I wanted it because no no I

00:45:34.440 --> 00:45:36.440
don't think it was

00:45:36.519 --> 00:45:38.679
in is in here because you said you

00:45:38.760 --> 00:45:41.360
weren't putting it

00:45:47.639 --> 00:45:49.159
in

00:45:49.239 --> 00:45:52.840
yeah can I have that is is that that

00:45:52.920 --> 00:45:54.000
that that one the other day where you

00:45:54.079 --> 00:45:58.519
had allocated the extra 6.5

00:45:59.119 --> 00:46:01.039
presentations sure I'm gonna go and say

00:46:01.119 --> 00:46:03.639
it then yeah sure thank you for

00:46:03.719 --> 00:46:07.599
that the  the point I was making was

00:46:07.679 --> 00:46:11.079
there is a in these draft documents

00:46:11.159 --> 00:46:13.519
there is actually a table that

00:46:13.599 --> 00:46:15.000
identifies

00:46:15.079 --> 00:46:18.280
where if it's adopted next year's SRV

00:46:18.360 --> 00:46:20.079
would be allocated to to what service

00:46:20.159 --> 00:46:22.480
areas I can't recall the page it was

00:46:22.559 --> 00:46:25.599
there before

00:46:25.679 --> 00:46:28.920
133 14

00:46:34.280 --> 00:46:39.599
133 yes any further questions

00:46:39.679 --> 00:46:44.320
count  could I ask staff to  just

00:46:44.400 --> 00:46:46.840
let us know what extra resources are

00:46:46.920 --> 00:46:49.079
going into planning services to overcome

00:46:49.159 --> 00:46:52.000
the backlogs we've got in  Das I

00:46:52.079 --> 00:46:55.480
looked at it it looks like we have very

00:46:55.559 --> 00:46:56.800
for completely the right reasons

00:46:56.880 --> 00:46:58.519
increase their investment in this area

00:46:58.599 --> 00:47:00.639
just like to know how it's allocated

00:47:00.719 --> 00:47:03.239
across strategic and da and building

00:47:03.320 --> 00:47:05.360
certification

00:47:05.440 --> 00:47:08.159
service through you Mr Mayor  in this

00:47:08.239 --> 00:47:11.599
budget we have  included a number of

00:47:11.679 --> 00:47:13.960
 additional resources or extended

00:47:14.039 --> 00:47:15.519
resources I should say in the planning

00:47:15.599 --> 00:47:18.280
space so that includes  we've extended

00:47:18.360 --> 00:47:19.719
a temporary development engineer

00:47:19.800 --> 00:47:22.559
position for the full Financial year 

00:47:22.639 --> 00:47:24.840
that isn't a a permanent position but

00:47:24.920 --> 00:47:26.960
was a decision  of Council of few

00:47:27.039 --> 00:47:28.880
years ago for some temporary resourcing

00:47:28.960 --> 00:47:31.320
to improve da assessment time frame so

00:47:31.400 --> 00:47:33.400
we've extended that for 12 months we've

00:47:33.480 --> 00:47:36.679
extended  a town planner contract

00:47:36.760 --> 00:47:39.239
position for another 12 months as well

00:47:39.320 --> 00:47:40.679
 it's currently filled at 3 days a

00:47:40.760 --> 00:47:42.360
week so we're looking to extend that for

00:47:42.440 --> 00:47:45.679
the full Financial year  we've also

00:47:45.760 --> 00:47:47.519
included some contractor budget in the

00:47:47.599 --> 00:47:50.880
environmental health area which will

00:47:50.960 --> 00:47:52.519
mean that we can prioritize what we call

00:47:52.599 --> 00:47:54.480
Da referrals so many Das have to go to

00:47:54.559 --> 00:47:56.360
our environmental health Team to look at

00:47:56.440 --> 00:47:58.639
 on it sewer management or water

00:47:58.719 --> 00:48:02.159
catchment  impacts so having a

00:48:02.239 --> 00:48:03.920
Contractor on board will mean we can do

00:48:04.000 --> 00:48:06.119
some of our legislated responsibilities

00:48:06.199 --> 00:48:08.800
for  health or Food Authority like

00:48:08.880 --> 00:48:10.719
food inspections of of registered

00:48:10.800 --> 00:48:12.800
premises  and then our staff can

00:48:12.880 --> 00:48:14.880
really focus on prioritizing the da

00:48:14.960 --> 00:48:17.880
referrals  we've also proposed

00:48:17.960 --> 00:48:19.239
extending a building support

00:48:19.320 --> 00:48:21.000
Administration officer role for another

00:48:21.079 --> 00:48:24.840
12 months  not isn't particularly to

00:48:24.920 --> 00:48:26.920
do with da assessment but it will help

00:48:27.000 --> 00:48:28.400
with that next stage when we get through

00:48:28.480 --> 00:48:29.639
the assessment and then looking at

00:48:29.719 --> 00:48:32.159
certification compliance  and there on

00:48:32.239 --> 00:48:34.639
so they're all different ways that we've

00:48:34.719 --> 00:48:37.800
invested or recommending we invest to

00:48:37.880 --> 00:48:40.800
help with our da time frames  the

00:48:40.880 --> 00:48:42.320
other thing oh sorry and then in terms

00:48:42.400 --> 00:48:44.800
of strategic planning  we have

00:48:44.880 --> 00:48:46.960
recommended  putting in it's I think

00:48:47.039 --> 00:48:48.000
it's

00:48:48.079 --> 00:48:50.239
106,000 this financial year that we're

00:48:50.320 --> 00:48:52.239
talking about to do some deliberate

00:48:52.320 --> 00:48:55.239
strategic planning work  around be and

00:48:55.320 --> 00:48:57.639
renewal and areu for Zone review which

00:48:57.719 --> 00:49:00.239
are particular  actions that have been

00:49:00.320 --> 00:49:03.400
identified in in adopted strategies 

00:49:03.480 --> 00:49:05.480
that we feel need to be prioritized in

00:49:05.559 --> 00:49:08.079
the 25 Financial

00:49:08.159 --> 00:49:11.440
Year Mr Mayor if I can just add  in

00:49:11.519 --> 00:49:14.239
terms of a focus on that area that isn't

00:49:14.320 --> 00:49:16.239
necessarily reflected in the budget is

00:49:16.320 --> 00:49:19.800
some of the  the other advocacy and

00:49:19.880 --> 00:49:22.719
programs that we've introduced as well

00:49:22.800 --> 00:49:25.039
and one of them is new Cadet ships in

00:49:25.119 --> 00:49:26.480
the current Financial year so it might

00:49:26.559 --> 00:49:27.159
be

00:49:27.239 --> 00:49:29.440
a little bit of time down the track to

00:49:29.519 --> 00:49:32.440
until we really start to see  what I

00:49:32.519 --> 00:49:33.800
might describe as the fruits of that

00:49:33.880 --> 00:49:35.800
investment but we've got great people in

00:49:35.880 --> 00:49:38.360
now and  and that'll help us a couple

00:49:38.440 --> 00:49:39.519
of years down the track so that's a

00:49:39.599 --> 00:49:41.639
future investment we've made now and

00:49:41.719 --> 00:49:43.880
that's actually a continuation of that

00:49:43.960 --> 00:49:45.559
is reflected in the budget that's before

00:49:45.639 --> 00:49:47.239
you now so that was a new thing this

00:49:47.320 --> 00:49:49.719
Current financial year  the other one

00:49:49.800 --> 00:49:52.400
is ongoing advocacy we've been 

00:49:52.480 --> 00:49:54.760
providing to the state government in

00:49:54.840 --> 00:49:58.119
particular around  train funding of

00:49:58.199 --> 00:50:01.239
training  and upskilling of existing

00:50:01.320 --> 00:50:02.599
Council employees and that's been

00:50:02.679 --> 00:50:03.679
successful and we're going to continue

00:50:03.760 --> 00:50:07.119
to advocate for that funding support 

00:50:07.199 --> 00:50:09.079
and we'll also be looking to do that at

00:50:09.159 --> 00:50:10.760
a federal level too to help the federal

00:50:10.840 --> 00:50:12.039
government understand that if they want

00:50:12.119 --> 00:50:13.639
to meet some of their housing targets

00:50:13.719 --> 00:50:16.000
and freeing up the supply of housing

00:50:16.079 --> 00:50:17.840
relies on planners to be able to get

00:50:17.920 --> 00:50:19.639
things done and and that's something

00:50:19.719 --> 00:50:21.920
we're contining to Advocate you see that

00:50:22.000 --> 00:50:23.800
you our advocacy priorities going

00:50:23.880 --> 00:50:27.280
forward too

00:50:27.360 --> 00:50:31.440
more questions any more questions

00:50:33.119 --> 00:50:36.519
Council can we add a counc like to add a

00:50:36.599 --> 00:50:38.960
point three to the recommendation yes I

00:50:39.039 --> 00:50:42.119
think it's on teams  but I can just

00:50:42.199 --> 00:50:43.760
read it out because Council Al won't

00:50:43.840 --> 00:50:46.280
have it on his teams say yep  so it's

00:50:46.360 --> 00:50:48.559
a new point three the council prepares a

00:50:48.639 --> 00:50:49.880
proposal for the New South Wales

00:50:49.960 --> 00:50:51.760
government seeking reform of the

00:50:51.840 --> 00:50:54.159
pensioner rebate which applies to about

00:50:54.239 --> 00:50:56.239
20% of bigger Valley's residential

00:50:56.320 --> 00:50:59.199
assess Ms so as to increase the rebate

00:50:59.280 --> 00:51:01.719
rebate and for the New South Wales

00:51:01.800 --> 00:51:03.719
government to fully fund the relief

00:51:03.800 --> 00:51:05.440
noting that the rebate will cost biger

00:51:05.519 --> 00:51:08.800
Valley sh more than 636,000 next

00:51:08.880 --> 00:51:11.400
financial

00:51:13.119 --> 00:51:17.000
year counc point three can you wish to

00:51:17.079 --> 00:51:20.000
speak to your motion thank you Mr Mayor

00:51:20.079 --> 00:51:22.119
Mr Mayor this is  and the discussion

00:51:22.199 --> 00:51:24.719
today has made it quite plain this is a

00:51:24.800 --> 00:51:27.559
very sobering time for

00:51:27.639 --> 00:51:30.760
 staff for counselors but it's more

00:51:30.840 --> 00:51:32.920
sabering for the general Community we

00:51:33.000 --> 00:51:34.480
all realize the hardships that are out

00:51:34.559 --> 00:51:36.639
there at the present time right across

00:51:36.719 --> 00:51:38.519
Australia for most Australians it's a

00:51:38.599 --> 00:51:40.679
very difficult time and it's a difficult

00:51:40.760 --> 00:51:43.000
time for councilors too to be resolving

00:51:43.079 --> 00:51:46.159
the way we we have resolved

00:51:46.239 --> 00:51:48.519
but when you look at these documents and

00:51:48.599 --> 00:51:49.159
the

00:51:49.239 --> 00:51:51.320
sabering discussions and Shing

00:51:51.400 --> 00:51:53.679
commentary within the documents it makes

00:51:53.760 --> 00:51:56.760
it very plain that if those 1.9 B ion

00:51:56.840 --> 00:51:59.320
dollar worth of our assets I use the

00:51:59.400 --> 00:52:02.199
word our because I'm a rate payer my

00:52:02.280 --> 00:52:04.639
family rate payers we're all basically

00:52:04.719 --> 00:52:07.960
rate payers and these are our assets

00:52:08.039 --> 00:52:09.440
this is our community these are our

00:52:09.519 --> 00:52:13.119
assets and  we can easily quite easily

00:52:13.199 --> 00:52:15.840
say no it's all too hard and let them

00:52:15.920 --> 00:52:18.320
deteriorate  let them

00:52:18.400 --> 00:52:21.239
depreciate  to the point where the

00:52:21.320 --> 00:52:23.840
place becomes basically unlivable or do

00:52:23.920 --> 00:52:26.000
we make the hard decisions as difficult

00:52:26.079 --> 00:52:27.119
as they are

00:52:27.199 --> 00:52:29.400
given the circstances that

00:52:29.480 --> 00:52:31.440
exist and and make the make the big

00:52:31.519 --> 00:52:33.760
calls so that's that's what we're doing

00:52:33.840 --> 00:52:36.000
today we're making that hard call we do

00:52:36.079 --> 00:52:38.119
it reluctantly and we do it with great

00:52:38.199 --> 00:52:39.800
respect to the people who will be

00:52:39.880 --> 00:52:42.039
affected by these calls it hasn't been

00:52:42.119 --> 00:52:43.400
resolved at Council but it's had for

00:52:43.480 --> 00:52:46.719
public exhibition and  I suspect

00:52:46.800 --> 00:52:48.840
suspect that the documents they're very

00:52:48.920 --> 00:52:51.320
involved  the very owners even for

00:52:51.400 --> 00:52:52.639
people like myself who have been here a

00:52:52.719 --> 00:52:55.320
long time to understand so I I'd suggest

00:52:55.400 --> 00:52:57.400
that not many people that they really

00:52:57.480 --> 00:53:00.079
can get their minds around them unless

00:53:00.159 --> 00:53:02.239
they're an acty or or an accountant 

00:53:02.320 --> 00:53:05.000
the ordinary ordinary ordinary person I

00:53:05.079 --> 00:53:07.840
that would really understand a lot of

00:53:07.920 --> 00:53:10.000
the docentation a lot of the wordage

00:53:10.079 --> 00:53:12.079
within the docentation but be that as

00:53:12.159 --> 00:53:13.559
it Mayor that's there the rules will be

00:53:13.639 --> 00:53:16.000
run by implemented by the state

00:53:16.079 --> 00:53:19.559
government  but to to support what

00:53:19.639 --> 00:53:23.199
we're doing we must understand too that

00:53:23.280 --> 00:53:26.960
of roughly 5% of the dollar that every

00:53:27.039 --> 00:53:30.719
person pays in tax roughly 5% of that

00:53:30.800 --> 00:53:32.920
dollar comes to local government for all

00:53:33.000 --> 00:53:35.360
the facilities we provide for all the

00:53:35.440 --> 00:53:38.440
services we provide we get about 5 cents

00:53:38.519 --> 00:53:41.039
in the tax dollar back to local

00:53:41.119 --> 00:53:45.119
government now that is a fact of life

00:53:45.199 --> 00:53:46.960
but it's wrong it's not enough and

00:53:47.039 --> 00:53:49.599
clearly not enough to maintain and

00:53:49.679 --> 00:53:53.480
provide and and might the living

00:53:53.559 --> 00:53:55.840
standards within our communities better

00:53:55.920 --> 00:53:57.280
it's not enough enough money the state

00:53:57.360 --> 00:53:59.360
government imposed this thing called

00:53:59.440 --> 00:54:02.320
rate pegging which is D is just an

00:54:02.400 --> 00:54:04.760
absolute mess it creates all sorts of

00:54:04.840 --> 00:54:06.760
havocs and then to overcome it we've

00:54:06.840 --> 00:54:08.880
then got to go cap in hand the staff

00:54:08.960 --> 00:54:11.239
have got to spend it months and months

00:54:11.320 --> 00:54:14.840
preparing docentation to seek special

00:54:14.920 --> 00:54:17.400
variation to keep the ship afloat we

00:54:17.480 --> 00:54:19.280
shouldn't have to do that we should be

00:54:19.360 --> 00:54:21.679
able to manage this business as we deal

00:54:21.760 --> 00:54:24.280
with water as we do with sewage as we de

00:54:24.360 --> 00:54:26.840
with waste based on our own

00:54:26.920 --> 00:54:28.880
ability to run the business but we're

00:54:28.960 --> 00:54:30.480
not allowed to do that the state

00:54:30.559 --> 00:54:31.800
government won't allow us to do that and

00:54:31.880 --> 00:54:33.360
I'm talking about both sides of politics

00:54:33.440 --> 00:54:35.800
here individually I don't know a

00:54:35.880 --> 00:54:38.239
politician who supports right pegging

00:54:38.320 --> 00:54:39.920
collectively they're they're they're

00:54:40.000 --> 00:54:41.679
they're a gutless legion because they

00:54:41.760 --> 00:54:43.719
all just get in behind the bandwagon and

00:54:43.800 --> 00:54:46.079
say it's got to it's got to occur and so

00:54:46.159 --> 00:54:48.400
it has occurred and it's it's it's it's

00:54:48.480 --> 00:54:51.159
making their life so difficult for all

00:54:51.239 --> 00:54:53.199
because you get to the point where you

00:54:53.280 --> 00:54:55.119
have to go and and take a big bite of

00:54:55.199 --> 00:54:57.039
the cherry and stay instead of taking

00:54:57.119 --> 00:54:58.599
incremental bites all along the way and

00:54:58.679 --> 00:55:00.559
keeping things aoat you get to the point

00:55:00.639 --> 00:55:02.280
where there's a point of no return and

00:55:02.360 --> 00:55:04.079
we have to go banging we've heard the

00:55:04.159 --> 00:55:05.920
docented today and Council n and

00:55:06.000 --> 00:55:08.000
others have raised it yester today which

00:55:08.079 --> 00:55:09.280
clearly

00:55:09.360 --> 00:55:11.760
shows that we're going further and

00:55:11.840 --> 00:55:14.719
further backwards if we don't address

00:55:14.800 --> 00:55:18.440
the ongoing situation of rising costs

00:55:18.519 --> 00:55:21.119
increased assets and more and more

00:55:21.199 --> 00:55:23.000
services that the community expect us to

00:55:23.079 --> 00:55:25.639
provide but in all in in most cases they

00:55:25.719 --> 00:55:27.519
expect those

00:55:27.599 --> 00:55:30.599
provided by bday bushe in other words

00:55:30.679 --> 00:55:32.599
who wants to pay for more services but

00:55:32.679 --> 00:55:33.960
if you don't pay for them that don't

00:55:34.039 --> 00:55:36.800
occur so it's a very difficult sit

00:55:36.880 --> 00:55:40.360
situation  we have responsibilities as

00:55:40.440 --> 00:55:43.280
as  counselors as I've said many times

00:55:43.360 --> 00:55:46.119
before and staff as well to address the

00:55:46.199 --> 00:55:48.920
issues that confront us as hard as that

00:55:49.000 --> 00:55:51.360
is and I think we've done that

00:55:51.440 --> 00:55:53.960
reasonably well not as not as well as we

00:55:54.039 --> 00:55:57.039
perhaps can in terms of the additional

00:55:57.119 --> 00:55:58.880
funding that will be needed to maintain

00:55:58.960 --> 00:56:02.280
the assets what concerns me a little bit

00:56:02.360 --> 00:56:05.639
is especially in my position over the

00:56:05.719 --> 00:56:08.000
years here is that we don't have the

00:56:08.079 --> 00:56:10.639
funds Now to turn any yellow Road into

00:56:10.719 --> 00:56:12.840
black  there was a time when we had

00:56:12.920 --> 00:56:15.400
plans and we did it we turned all the 

00:56:15.480 --> 00:56:18.840
Village roads Village dirt roads into

00:56:18.920 --> 00:56:21.400
sealed roads and we were sealing roads

00:56:21.480 --> 00:56:23.480
throughout the sh we can only do that

00:56:23.559 --> 00:56:24.960
now through grant funding and that's

00:56:25.039 --> 00:56:27.159
that's that's just a way is  we're

00:56:27.239 --> 00:56:29.119
dependent on both federal government and

00:56:29.199 --> 00:56:31.920
state government that matter to allocate

00:56:32.000 --> 00:56:34.880
more funds to us for the improvements

00:56:34.960 --> 00:56:37.400
that we should be get having and getting

00:56:37.480 --> 00:56:39.280
 for our communities and but that's

00:56:39.360 --> 00:56:40.880
just that's the way it is at the present

00:56:40.960 --> 00:56:43.679
time so Mr Mayor it's not it's not a

00:56:43.760 --> 00:56:46.480
it's not a  docent that we  relish

00:56:46.559 --> 00:56:48.960
it's a very saing do docent and it's

00:56:49.039 --> 00:56:51.480
one that  it goate to their hearts in

00:56:51.559 --> 00:56:53.679
terms of of the decisions we have to

00:56:53.760 --> 00:56:56.639
make but we have to make them and  

00:56:56.719 --> 00:57:01.880
the the  assets be that is getting

00:57:01.960 --> 00:57:03.320
close to $2 billion have to be

00:57:03.400 --> 00:57:04.800
maintained as simple is that the water

00:57:04.880 --> 00:57:06.760
has to flow the sewage has to flow the

00:57:06.840 --> 00:57:08.840
garbage has to be picked up and and

00:57:08.920 --> 00:57:10.320
above all we've got to have a reasonable

00:57:10.400 --> 00:57:13.199
transport system because mothers have to

00:57:13.280 --> 00:57:15.280
know that when it they pick the children

00:57:15.360 --> 00:57:17.079
in the car to go to school of a Monday

00:57:17.159 --> 00:57:20.000
morning go to the bus the transport

00:57:20.079 --> 00:57:22.079
system must allow that to happen so

00:57:22.159 --> 00:57:23.719
that's a huge responsibility for us all

00:57:23.800 --> 00:57:25.280
and  it's one we've just got to

00:57:25.360 --> 00:57:27.039
address and we were doing our best to

00:57:27.119 --> 00:57:29.880
address it thank you Mr me thanks any

00:57:29.960 --> 00:57:31.400
other speaker

00:57:31.480 --> 00:57:36.000
against speak for Council as your

00:57:39.760 --> 00:57:42.000
second that's all right  thank you I

00:57:42.079 --> 00:57:44.480
just can Echo  Council Allen's

00:57:44.559 --> 00:57:45.840
statements there especially when it

00:57:45.920 --> 00:57:48.280
comes to cost shifting for both levels

00:57:48.360 --> 00:57:50.760
of go government particularly the state

00:57:50.840 --> 00:57:52.239
government as well and I mean I thank

00:57:52.320 --> 00:57:53.760
you councelor O'Neal for putting in the

00:57:53.840 --> 00:57:55.039
extra dot

00:57:55.119 --> 00:57:57.400
point I mean you could put in several

00:57:57.480 --> 00:57:59.280
dot points about

00:57:59.360 --> 00:58:02.199
 things you want to Advocate and you

00:58:02.280 --> 00:58:03.559
know for what it's worth I was actually

00:58:03.639 --> 00:58:05.960
going to make particular  thanks to

00:58:06.039 --> 00:58:08.840
the Jo  country Mayors as well and the

00:58:08.920 --> 00:58:10.559
work that we're doing internally in this

00:58:10.639 --> 00:58:13.360
Council  I know that that that when

00:58:13.440 --> 00:58:15.960
the  state government Hears A biger

00:58:16.039 --> 00:58:20.480
Valley they do listen and  we  and

00:58:20.559 --> 00:58:22.400
so for that I'm I'm grateful for the ad

00:58:22.480 --> 00:58:24.440
advocacy that they that we do but it's

00:58:24.519 --> 00:58:25.679
it's time for them to actually sit down

00:58:25.760 --> 00:58:27.719
and listen now and I hope that part of

00:58:27.800 --> 00:58:29.639
these standing that committees that

00:58:29.719 --> 00:58:30.840
they're doing into Financial

00:58:30.920 --> 00:58:32.519
sustainability of council that they'll

00:58:32.599 --> 00:58:34.480
actually listen the one thing that isn't

00:58:34.559 --> 00:58:36.800
addressed sometimes though in those 

00:58:36.880 --> 00:58:38.880
in those reports is our own ability to

00:58:38.960 --> 00:58:40.800
create sorry our ability to create our

00:58:40.880 --> 00:58:43.920
own Revenue as well  the CEO and I

00:58:44.000 --> 00:58:46.320
have had several talks about this about

00:58:46.400 --> 00:58:48.320
the limitations around us and

00:58:48.400 --> 00:58:50.599
anti-competition rules and whatever it

00:58:50.679 --> 00:58:52.840
might be about councils actually having

00:58:52.920 --> 00:58:54.280
the ability to generate their own

00:58:54.360 --> 00:58:56.480
Revenue which I think is a real shame 

00:58:56.559 --> 00:58:58.559
especially in Regional areas as well

00:58:58.639 --> 00:59:00.760
where we could be you know a part of

00:59:00.840 --> 00:59:03.039
that  wider economic growth in the

00:59:03.119 --> 00:59:04.880
area and take and have the ability to

00:59:04.960 --> 00:59:06.920
take pressure off our  of our rate

00:59:07.000 --> 00:59:08.800
payers in doing so so I think that

00:59:08.880 --> 00:59:10.280
that's something that should be 

00:59:10.360 --> 00:59:13.239
looked at in the future  just back to

00:59:13.320 --> 00:59:15.639
the budget  I think that that is a

00:59:15.719 --> 00:59:17.360
really important point we're only paying

00:59:17.440 --> 00:59:20.119
for 66%  at the moment of funded of

00:59:20.199 --> 00:59:22.960
our roads Network  so whatever you

00:59:23.039 --> 00:59:25.199
decide in this budget it's on exhibition

00:59:25.280 --> 00:59:27.400
and 

00:59:27.480 --> 00:59:30.239
the makeup of it at the moment I

00:59:30.320 --> 00:59:34.400
certainly am am not keen for  I think

00:59:34.480 --> 00:59:35.920
that a few things need to be mixed

00:59:36.000 --> 00:59:37.679
around my priorities aren't necessarily

00:59:37.760 --> 00:59:40.000
aligned with with that docent so I'll

00:59:40.079 --> 00:59:42.199
I'll just flag that and I think the Mayor

00:59:42.280 --> 00:59:43.679
said  we should be making our own

00:59:43.760 --> 00:59:45.880
submissions that's fine I will do that

00:59:45.960 --> 00:59:47.039
 so that's all right I also want to

00:59:47.119 --> 00:59:50.480
thank the staff for A really lovely

00:59:50.559 --> 00:59:53.920
written and presented a budget  it is

00:59:54.000 --> 00:59:56.280
very readable and the design is great

00:59:56.360 --> 00:59:58.679
and that's fantastic  I've had a bit

00:59:58.760 --> 01:00:00.719
of a chat with il about it the only

01:00:00.800 --> 01:00:02.480
thing that I could say that I'd love to

01:00:02.559 --> 01:00:05.440
see for the benefit  of everyone is

01:00:05.519 --> 01:00:07.480
you know operational plan  when it

01:00:07.559 --> 01:00:08.880
goes through the different  cost

01:00:08.960 --> 01:00:11.280
centers is to attach some sort of 

01:00:11.360 --> 01:00:14.159
yeah   capex to it so that you can

01:00:14.239 --> 01:00:16.360
actually see where the budget is you can

01:00:16.440 --> 01:00:17.679
you can get a sense of what they're

01:00:17.760 --> 01:00:19.159
actually doing more than just Core

01:00:19.239 --> 01:00:20.679
Business is great you know we cleaned

01:00:20.760 --> 01:00:23.559
the toilets we this year however we're

01:00:23.639 --> 01:00:26.360
replacing for by the way we're not but

01:00:26.440 --> 01:00:29.079
you know the hypthetically replacing a

01:00:29.159 --> 01:00:30.679
you know three toilets one in be one in

01:00:30.760 --> 01:00:33.079
Maringa one in Eden so that would be a

01:00:33.159 --> 01:00:34.199
great thing to have and just a little

01:00:34.280 --> 01:00:36.400
bit of extra detail I think for everyone

01:00:36.480 --> 01:00:38.719
 but yeah so there's so in terms of

01:00:38.800 --> 01:00:41.199
putting this on public exhibition 

01:00:41.280 --> 01:00:42.719
yeah I mean I don't know how many people

01:00:42.800 --> 01:00:44.440
read this docent but more than ever

01:00:44.519 --> 01:00:46.000
should be reading it because it is

01:00:46.079 --> 01:00:49.360
readable so  I look forward to to

01:00:49.440 --> 01:00:50.880
hearing what people have to say and I

01:00:50.960 --> 01:00:52.559
look forward to a revised budget plan

01:00:52.639 --> 01:00:53.400
with some of those things that I

01:00:53.480 --> 01:00:56.039
mentioned in the beginning   as as

01:00:56.119 --> 01:00:57.480
well some of those extra costs that

01:00:57.559 --> 01:01:00.320
we've incurred recently so thank

01:01:00.400 --> 01:01:03.440
you speaker against speaker councel you

01:01:03.519 --> 01:01:06.920
want to speak  thank you Mr Mayor 

01:01:07.000 --> 01:01:09.920
two points to add  the first one is

01:01:10.000 --> 01:01:12.480
looking at the 23 strategies and our

01:01:12.559 --> 01:01:15.079
operating plan  at the moment under

01:01:15.159 --> 01:01:17.679
our community strategic plan we've got

01:01:17.760 --> 01:01:19.760
such a wide range of themes and

01:01:19.840 --> 01:01:22.079
objectives so I urge people who are

01:01:22.159 --> 01:01:23.679
looking at these accounts just to look

01:01:23.760 --> 01:01:25.079
at the wide range of things we're

01:01:25.159 --> 01:01:26.559
involved in

01:01:26.639 --> 01:01:28.239
 but I also want to make that the

01:01:28.320 --> 01:01:31.559
point in that we all the the themes and

01:01:31.639 --> 01:01:34.159
the objectives in those 23 strategies if

01:01:34.239 --> 01:01:35.599
we want to achieve there it's going to

01:01:35.679 --> 01:01:38.039
need work by a lot of players both the

01:01:38.119 --> 01:01:39.679
government and within the community get

01:01:39.760 --> 01:01:43.320
there so Mayorbe as we discussed the draft

01:01:43.400 --> 01:01:45.719
leading up to our June 26 final meeting

01:01:45.800 --> 01:01:48.000
on this we sort of clarify where the

01:01:48.079 --> 01:01:49.719
council needs to set its priorities

01:01:49.800 --> 01:01:53.960
within those 23 strategies  otherwise

01:01:54.039 --> 01:01:55.519
there's not so much guidance to staff

01:01:55.599 --> 01:01:59.119
there of where to to focus  and

01:01:59.199 --> 01:02:00.800
reiterating that if you look down the

01:02:00.880 --> 01:02:02.679
back of the Strategic assets management

01:02:02.760 --> 01:02:05.239
plan of the shortfalls in spending on

01:02:05.320 --> 01:02:07.079
some of our core areas in roads and

01:02:07.159 --> 01:02:09.159
bridges it's really something we're all

01:02:09.239 --> 01:02:11.360
going to have to focus on over the next

01:02:11.440 --> 01:02:14.440
year the special rate variation has

01:02:14.519 --> 01:02:16.800
bought its time now it's all of our

01:02:16.880 --> 01:02:18.639
responsibility to actually look at what

01:02:18.719 --> 01:02:20.880
we must do what we cannot do and

01:02:20.960 --> 01:02:23.920
advocate for the gap which brings me to

01:02:24.000 --> 01:02:26.159
my second Point  the reason I

01:02:26.239 --> 01:02:27.440
suggested we add the point about the

01:02:27.519 --> 01:02:30.639
pension of rebate is that  as the

01:02:30.719 --> 01:02:33.480
Mayor gets ready to go with the 

01:02:33.559 --> 01:02:35.960
Regional joint organization up to Sydney

01:02:36.039 --> 01:02:37.639
to

01:02:37.719 --> 01:02:40.360
Advocate these documents say we one of

01:02:40.440 --> 01:02:42.639
the biggest shes all on the coast of New

01:02:42.719 --> 01:02:45.400
South Wales we have a population with an

01:02:45.480 --> 01:02:48.360
average age of 52 so far above the state

01:02:48.440 --> 01:02:50.239
average things like the pension or

01:02:50.320 --> 01:02:53.760
rebate hits us far more than it hits

01:02:53.840 --> 01:02:56.760
either Western New South Wales or 

01:02:56.840 --> 01:02:59.440
urban New South Wales and we need to

01:02:59.519 --> 01:03:01.119
really bring it home to as many people

01:03:01.199 --> 01:03:04.480
as possible that in some cases we are

01:03:04.559 --> 01:03:06.559
hit particularly hard by things which

01:03:06.639 --> 01:03:08.639
can be changed and should be changed

01:03:08.719 --> 01:03:11.039
like the pension or rebate  I think

01:03:11.119 --> 01:03:12.199
the last time we looked at this it

01:03:12.280 --> 01:03:13.519
looked like the pension or rebate

01:03:13.599 --> 01:03:15.079
legislation hadn't been looked after for

01:03:15.159 --> 01:03:17.800
some decades it's well overdue and

01:03:17.880 --> 01:03:19.039
something that can be fixed up in the

01:03:19.119 --> 01:03:21.719
next year and help our local residents

01:03:21.800 --> 01:03:24.119
while still retaining support for

01:03:24.199 --> 01:03:25.719
low-income members of the community

01:03:25.800 --> 01:03:28.159
which is essential I think I mean the

01:03:28.239 --> 01:03:29.800
pension of rebate is an very important

01:03:29.880 --> 01:03:32.280
tool for getting equal access to

01:03:32.360 --> 01:03:35.800
services but unless bigger Valley shy

01:03:35.880 --> 01:03:37.599
gets more money we can't provide an

01:03:37.679 --> 01:03:39.760
adequate service level for our community

01:03:39.840 --> 01:03:43.679
members thank you than no anyone else

01:03:43.760 --> 01:03:48.639
wish to speak just briefly well coun

01:03:48.719 --> 01:03:50.920
says there some pretty hard sobering

01:03:51.000 --> 01:03:52.679
things in here I totally agree because

01:03:52.760 --> 01:03:54.440
we've known that for a while but there

01:03:54.519 --> 01:03:56.159
is some good news in here I look at the

01:03:56.239 --> 01:03:57.880
road spend and we've brought that's been

01:03:57.960 --> 01:03:59.880
brought up several times but in the next

01:03:59.960 --> 01:04:02.000
budget Year we're talking about a spend

01:04:02.079 --> 01:04:05.440
on sealed roads of 11.7 million 5

01:04:05.519 --> 01:04:08.079
million of that is capital  on Bridges

01:04:08.159 --> 01:04:09.559
we're talking to spend of 9 million but

01:04:09.639 --> 01:04:11.559
it's all capital because we've got some

01:04:11.639 --> 01:04:13.280
 Bridges through fixing country

01:04:13.360 --> 01:04:14.920
Bridges progr that's no

01:04:15.000 --> 01:04:17.679
longer provided anymore but they were

01:04:17.760 --> 01:04:20.039
successful grants that the staff got and

01:04:20.119 --> 01:04:21.559
allowed us to do some other Bridges so

01:04:21.639 --> 01:04:23.320
there is some good news in there there I

01:04:23.400 --> 01:04:25.199
think it's $8 million to be spent on

01:04:25.280 --> 01:04:26.599
sports grounds or recreational

01:04:26.679 --> 01:04:29.360
facilities as well across the board so

01:04:29.440 --> 01:04:31.320
there is quite a quite a big spend in

01:04:31.400 --> 01:04:32.559
some areas our sporting ground

01:04:32.639 --> 01:04:34.480
facilities was a total 11 million most

01:04:34.559 --> 01:04:36.159
of that is capital of course with a be

01:04:36.239 --> 01:04:38.159
and P the sporting R but it's still a

01:04:38.239 --> 01:04:40.400
$1.2 million spend out our operational

01:04:40.480 --> 01:04:42.400
money on our Sports grounds which is

01:04:42.480 --> 01:04:44.519
quite an achievement for when we have so

01:04:44.599 --> 01:04:47.119
many sports grounds in the P the

01:04:47.199 --> 01:04:49.280
picturesque way they look at the present

01:04:49.360 --> 01:04:51.239
time down at George Brown this morning

01:04:51.320 --> 01:04:52.280
it's quite incredible how that ground

01:04:52.360 --> 01:04:54.960
over looks as well  so yeah I totally

01:04:55.039 --> 01:04:58.199
concur with everyone said and  agree

01:04:58.280 --> 01:04:59.840
with comments of everyone there's other

01:04:59.920 --> 01:05:01.639
areas we can look at I'm try and save

01:05:01.719 --> 01:05:03.440
costs and making sure that we don't go

01:05:03.519 --> 01:05:05.440
ahead with things that as Council a

01:05:05.519 --> 01:05:06.800
alluded to you know that we have another

01:05:06.880 --> 01:05:08.320
look at the youth space the way we go

01:05:08.400 --> 01:05:10.360
there as as well as Tia Beach as those

01:05:10.440 --> 01:05:12.400
come forward and start bring them to us

01:05:12.480 --> 01:05:14.440
from time to time so it's important that

01:05:14.519 --> 01:05:16.800
we we keep our eyes on those costings in

01:05:16.880 --> 01:05:18.360
those little projects that we keep them

01:05:18.440 --> 01:05:20.599
under control thank you

01:05:20.679 --> 01:05:22.840
councilors Council Al you want any WR a

01:05:22.920 --> 01:05:26.199
reply put the motion all those in favor

01:05:26.280 --> 01:05:27.960
very dous thanks

01:05:28.039 --> 01:05:29.639
counselors

01:05:29.719 --> 01:05:32.400
no no council reports no recision

01:05:32.480 --> 01:05:34.840
alterations motions no notice motions

01:05:34.920 --> 01:05:36.679
questions with no questions with notice

01:05:36.760 --> 01:05:40.880
questions without no counil

01:05:40.960 --> 01:05:44.199
coun yeah sorry Mr Mayor just an update

01:05:44.280 --> 01:05:45.199
if

01:05:45.280 --> 01:05:48.400
 St would mind on the void counter

01:05:48.480 --> 01:05:49.920
State

01:05:50.000 --> 01:05:54.000
 subdivision

01:05:55.760 --> 01:05:58.920
take that on Noti and bring

01:05:59.519 --> 01:06:02.159
answer  would the council staff 

01:06:02.239 --> 01:06:04.159
update us on the number of Da lodged and

01:06:04.239 --> 01:06:06.440
determined in the the recent quarter

01:06:06.519 --> 01:06:09.039
including processing times noting that

01:06:09.119 --> 01:06:11.440
the New South Wales portal tracker is

01:06:11.519 --> 01:06:13.039
actually saying that bigger Valley is

01:06:13.119 --> 01:06:15.599
taking a gross number of days of 165 and

01:06:15.679 --> 01:06:19.199
I understand we are doing better than

01:06:20.559 --> 01:06:23.480
that sure you Mr Mayor  I do have a

01:06:23.559 --> 01:06:25.519
report coming to the next Council

01:06:25.599 --> 01:06:27.119
meeting the 22 Mayor council meeting that

01:06:27.199 --> 01:06:28.639
will explain the statistics in more

01:06:28.719 --> 01:06:30.440
detail but I can give you an overview

01:06:30.519 --> 01:06:34.599
now  we are tracking our da statistics

01:06:34.679 --> 01:06:36.800
quarterly so for the first quarter of

01:06:36.880 --> 01:06:39.719
this calendar year January to March 

01:06:39.800 --> 01:06:43.360
our average net da processing time is

01:06:43.440 --> 01:06:45.840
86.1 5 days which has come down

01:06:45.920 --> 01:06:47.760
significantly from

01:06:47.840 --> 01:06:50.440
117.8 s days at the end of the last

01:06:50.519 --> 01:06:54.119
calendar year  that is a significant

01:06:54.199 --> 01:06:56.599
you know Improvement  and it's du to a

01:06:56.679 --> 01:06:58.360
lot of effort on behalf of the staff and

01:06:58.440 --> 01:07:00.679
staff right across the organization 

01:07:00.760 --> 01:07:04.400
it is still too early to know if that is

01:07:04.480 --> 01:07:06.039
sustainable because it is dependent on

01:07:06.119 --> 01:07:07.480
the number of Das that are coming in as

01:07:07.559 --> 01:07:09.679
well on the complexity of Das but it is

01:07:09.760 --> 01:07:11.320
promising to see that our assessment

01:07:11.400 --> 01:07:13.719
times are decreasing now that is net

01:07:13.800 --> 01:07:16.880
average assessment  processing times

01:07:16.960 --> 01:07:20.039
 the difference between net and gross

01:07:20.119 --> 01:07:21.719
processing times which I reported on as

01:07:21.800 --> 01:07:24.159
well gross processing times include stop

01:07:24.239 --> 01:07:26.079
clock what stop clock

01:07:26.159 --> 01:07:28.159
 time is is if we have to request

01:07:28.239 --> 01:07:29.360
additional information from the

01:07:29.440 --> 01:07:31.599
applicant so if they haven't addressed

01:07:31.679 --> 01:07:32.440
 an

01:07:32.519 --> 01:07:34.840
element adequately and we need to go

01:07:34.920 --> 01:07:36.199
back for further information and we're

01:07:36.280 --> 01:07:38.119
waiting on the applicant to provide that

01:07:38.199 --> 01:07:40.079
that's we call that stop clock and we

01:07:40.159 --> 01:07:41.760
don't count that in the net processing

01:07:41.840 --> 01:07:42.840
times because there's nothing that we

01:07:42.920 --> 01:07:44.559
can do from our perspective to keep that

01:07:44.639 --> 01:07:49.079
da moving  in terms of Da numbers that

01:07:49.159 --> 01:07:50.960
have been

01:07:51.039 --> 01:07:56.960
determined  sorry I'm just finding

01:07:57.039 --> 01:08:01.519
that's in the 2023 Financial year we

01:08:01.599 --> 01:08:05.079
determined 414 Das across the whole

01:08:05.159 --> 01:08:06.920
calendar year  in the first three

01:08:07.000 --> 01:08:09.400
months of this year we've determined 70

01:08:09.480 --> 01:08:12.000
now the numbers that we get out each

01:08:12.079 --> 01:08:13.480
quarter do depend on the complexity of

01:08:13.559 --> 01:08:14.679
the Das that we're looking at so if

01:08:14.760 --> 01:08:17.359
we're looking at  larger developments

01:08:17.439 --> 01:08:19.399
they take a lot longer than simple

01:08:19.479 --> 01:08:20.720
houses or

01:08:20.800 --> 01:08:24.000
sheds sorry councelor does that provide

01:08:24.079 --> 01:08:25.640
you with an overview for now and more a

01:08:25.720 --> 01:08:26.800
report will be coming to the next

01:08:26.880 --> 01:08:29.680
meeting thank you very much Council any

01:08:29.760 --> 01:08:30.600
further

01:08:30.680 --> 01:08:33.039
questions no further questions Council

01:08:33.119 --> 01:08:38.079
close the meeting at 308 thank you